Bhadar Riverbed Paiki Village.Nagnesh,Ta.Ranpur,Dist.Botad 02.00.00 (Dharmendrasinh Jasubha Zala) is an approved mining project in Kinara, Ranpur, Botad, Gujarat. The site covers 4.9 acres.
Who is building it?
The applicant is Gambhirsinh Hathibha Zala.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Mar 2025), as of 27 Nov 2026.
Where is it?
In Kinara, Ranpur, Botad, Gujarat.
How big is it?
It has a stated cost of ₹10 lakh and a site of 4.9 acres.
When was it filed?
The application was filed on 17 Oct 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Mar 2025 |
| Application filed | 17 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Gambhirsinh Hathibha Zala |
| Land area | 4.9 acres (2 ha) |
| Project cost | ₹10 lakh |
| Village / locality | Kinara |
| Taluk / tehsil | Ranpur |
| District | Botad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-03400 |
In context
58 applications in Botad since January 2022 are in the same category (Mining): 24 approved, 22 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 4.9 acres, this one is smaller than 52% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 9.9 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 22 mining leases have applied within 5 km.
Where it is
Kinara, Ranpur, Botad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Dharmendrasinh Jasubha Zala — returned to applicant, 0 m away
- Jasubha Banubha Zala — lapsed, 200 m away
- Ghanshyamsinh Hemubha Zala(Survey No.Bhadar Riverbed Paiki… — lapsed, 550 m away
- Ghanshyamsinh Hemubha Zala(Survey No.Bhadar Riverbed… — not approved, 550 m away
- Ghanshyamsinh Hemubha Zala — returned to applicant, 550 m away
- Ordinary Sand Mining Project — lapsed, 700 m away
- Zala Ranjitsinh Banubha ( Nagnesh Ordinary Sand Mine ) — environmental approval granted, 700 m away
- Zala Ranjitsinh Banubha ( Nagnesh Ordinary Sand Mine ) — lapsed, 700 m away
More from Gambhirsinh Hathibha Zala in Botad
- Nagnesh Ordinary Sand Mine 02.00.00 (Gambhirsinh Hathibha Zala) — environmental approval granted
- Dharmendrasinh Jasubha Zala — returned to applicant