Cleared for impact studyBuildings & townships · Ahmadabad, Gujarat

Arvind Lake City

Arvind Lake City is a proposed township project in Kesrandi, Bavla, Ahmadabad, Gujarat. It plans 5,523 units of up to 14 floors on 510.1 acres. Its stated project cost is ₹1,103.5 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 3 Aug 2024).

See it on the live map All projects in Ahmadabad

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusCleared for impact study
Status since3 Aug 2024
Application filed4 Apr 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorBuildings & townships
ApplicantKalyangadh Homes LLP
UseTownship
Units5,523
Floors (tallest)14
Basements2
Land area510.1 acres (206.4 ha)
Built-up area11,63,882 m² (1,25,27,909 sq ft)
Plot area20,64,260 m² (2,22,19,488 sq ft)
Project cost₹1,103.5 crore
Village / localityKesrandi
Taluk / tehsilBavla
DistrictAhmadabad
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-03706

In context

1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 510.1 acres, this one is larger than 99% of them.

12 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kesrandi, Bavla, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Kalyangadh Homes LLP in Ahmadabad

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.