Shri jasvantsinh rathod Re-Appraisal Mining of Black Trap Thoriyali Black Trap Quarry lease is a rejected mining project in Thoriyali, Sayla, Surendranagar, Gujarat. The site covers 7.4 acres.
Who is building it?
The applicant is Rathod Jasvantsinh a.
Has it been approved?
No. The application was rejected on 27 Mar 2025.
Where is it?
In Thoriyali, Sayla, Surendranagar, Gujarat.
How big is it?
It has a stated cost of ₹2.4 crore and a site of 7.4 acres.
When was it filed?
The application was filed on 7 Sept 2024.
Project details
| Official title | Shri jasvantsinh rathod Re-Appraisal Mining of Black Trap Thoriyali Black Trap Quarry lease situated at Village - Thoriyali admeasuring 03.00.00 Ha area at Survey number 194 Paiki, near Village: - Thoriyali, Taluka: - Sayla, District: - Surendranagar, State: - Gujarat |
|---|---|
| Status | Not approved |
| Status since | 27 Mar 2025 |
| Application filed | 7 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Rathod Jasvantsinh a |
| Land area | 7.4 acres (3 ha) |
| Project cost | ₹2.4 crore |
| Village / locality | Thoriyali |
| Taluk / tehsil | Sayla |
| District | Surendranagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-04220 |
In context
271 applications in Surendranagar since January 2022 are in the same category (Mining): 107 approved, 59 filed or under review, and 105 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 7.4 acres, this one is larger than 72% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 11.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 30 mining leases have applied within 5 km.
Where it is
Thoriyali, Sayla, Surendranagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shri Gambhirsinh Agarsinh Rathod Re-Appraisal Mining of Black Trap Thoriyali… — not approved, 300 m away
- Govindbhai Pathubhai Rathod Re-Appraisal Mining of Black Trap Thoriyali Black… — not approved, 600 m away
- Shree Pruthvirajsinh Kiritsinh Rana Re-Appraisal Mining of Black Trap… — environmental approval granted, 600 m away
- Shri Alabhai Virabhai Rabari — returned to applicant, 700 m away
- Shri Virabhai Devabhai Rabari — returned to applicant, 800 m away
- Shri Vijaybhai Manubhai Makwana Re-Appraisal Mining of Black Trap Thoriyali… — environmental approval granted, 1.1 km away
- Shri ishubhai shekhawat Re-Appraisal Mining of Black Trap Thoriyali Black Trap… — environmental approval granted, 1.1 km away