Quick answers
What is Shri Alabhai Virabhai Rabari?
Shri Alabhai Virabhai Rabari is a proposed mining project in Thoriyali, Sayla, Surendranagar, Gujarat. The site covers 2.5 acres.
Who is building it?
The applicant is Khavad Champarajbhai B.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Thoriyali, Sayla, Surendranagar, Gujarat.
How big is it?
It has a stated cost of ₹2.6 crore and a site of 2.5 acres.
When was it filed?
The application was filed on 15 Mar 2025.
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 25 Mar 2025 |
| Application filed | 15 Mar 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Khavad Champarajbhai B |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹2.6 crore |
| Village / locality | Thoriyali |
| Taluk / tehsil | Sayla |
| District | Surendranagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06955 |
In context
271 applications in Surendranagar since January 2022 are in the same category (Mining): 107 approved, 59 filed or under review, and 105 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.5 acres, this one is smaller than 97% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 15.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 24 mining leases have applied within 5 km.
Where it is
Thoriyali, Sayla, Surendranagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Govindbhai Pathubhai Rathod Re-Appraisal Mining of Black Trap Thoriyali Black… — not approved, 150 m away
- Shri Virabhai Devabhai Rabari — returned to applicant, 150 m away
- Shri Gambhirsinh Agarsinh Rathod Re-Appraisal Mining of Black Trap Thoriyali… — not approved, 400 m away
- Shri jasvantsinh rathod Re-Appraisal Mining of Black Trap Thoriyali Black Trap… — not approved, 700 m away
- Shree Pruthvirajsinh Kiritsinh Rana Re-Appraisal Mining of Black Trap… — environmental approval granted, 900 m away
- Shri ishubhai shekhawat Re-Appraisal Mining of Black Trap Thoriyali Black Trap… — environmental approval granted, 1.1 km away
- Juna Jashapar Black Trap Mine — lapsed, 1.1 km away
- Shree Arjanbhai Vahanbhai Jograna Re-Appraisal Mining of Black Trap. Juna… — not approved, 1.3 km away
More from Khavad Champarajbhai B in Surendranagar
- Late Shri Muljibhai Dahyabhai Makwana Heir Shri Vijaybhai Muljibhai Msakwana — returned to applicant
- Shri Khavad Champrajbhai Bhupatbhai — returned to applicant
- Shri Virabhai Devabhai Rabari — returned to applicant
- Shri Aapabhai Vershibhai Rabari — returned to applicant
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.