| Status | Environmental approval granted |
|---|---|
| Status since | 9 Aug 2024 |
| Application filed | 23 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Mirvan Reality |
| Use | Residential |
| Units | 156 |
| Towers | 3 |
| Floors (tallest) | 13 |
| Basements | 2 |
| Parking spaces | 230 |
| Land area | 1.2 acres (0.5 ha) |
| Built-up area | 33,148 m² (3,56,802 sq ft) |
| Plot area | 5,044 m² (54,293 sq ft) |
| Project cost | ₹53.7 crore |
| Village / locality | Nikol |
| Taluk / tehsil | Sabarmati |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-04310 |
What the filings say
What is planned
Mirvan Reality proposes to develop Asopalav Green, a new residential building project in Nikol, Ahmedabad. The applicant's project report describes a development consisting of three blocks (A, B, and C) with a total of 156 residential units. The buildings are designed with two basements, a ground floor or hollow plinth, and 13 upper floors.
According to the area table, the project has a total built-up area of 33,148.20 square metres on a plot of 5,044.21 square metres. The total permissible Floor Space Index (FSI) area is 19,820.06 square metres, all of which is utilized in the proposal.
| Item | Detail |
|---|---|
| Total Units | 156 residential flats |
| Total Built-up Area | 33,148.20 square metres |
| Total FSI Area | 19,820.06 square metres |
| Tallest Building | 2 Basements + Ground + 13 Floors |
| Estimated Population | 624 persons |
| Power Requirement | 980 KW |
| Backup Power | 125 KVA DG set (1 unit) |
Layout and design
The site layout includes internal approach roads of 12.0 metres and 9.0 metres width, with entry to the premises provided through an 18.0-metre wide road. The project includes a common plot area of 508.91 square metres and a dedicated greenbelt area of 762.91 square metres.
Parking is planned across two basement levels and the ground floor. The applicant proposes a total parking area of 7,157.06 square metres, providing space for 230 Equivalent Car Spaces (ECS). This exceeds the local Gujarat Development Control Regulations (GDCR) requirement of 3,964.01 square metres.
Land and surroundings
The project is located at Final Plot No. 117/2 in Nikol, within the Ahmedabad Municipal Corporation (AMC) limits. The site coordinates range approximately from 23° 3'4"N to 23° 3'6"N latitude and 72° 40'46"E to 72° 40'51"E longitude. The surrounding area is primarily residential. The nearest railway station is Sardargam Cabin Station, located 4.44 km away, and Ahmedabad Airport is approximately 6.28 km from the site. The project falls under Seismic Zone III, indicating a medium probability of earthquake shocks.
Water, power and access
During the operational phase, the total water requirement is estimated at 88.1 kilolitres per day (KLD). Fresh water demand of 56.4 KLD will be met by the AMC water supply. The remaining 31.6 KLD will be met through recycled treated sewage for flushing and gardening.
Sewage generation is estimated at 71.6 KLD. The applicant plans to install an on-site Sewage Treatment Plant (STP). Treated water will be reused, and the surplus (approximately 40.0 KLD) will be discharged into the AMC drainage line. For rainwater management, two percolation wells are proposed to recharge ground water aquifers.
Electricity will be sourced from Uttar Gujarat Vij Company Limited (UGVCL). The project design incorporates energy conservation measures such as LED lighting, solar street lights, and architectural features like cantilever balconies to provide shading and reduce cooling loads.
Environmental safeguards
The applicant has budgeted ₹2.15 crore for capital environmental management costs and ₹10.35 lakh for annual operation and maintenance. Key safeguards include:
- Waste Management: An Organic Waste Converter will be used for biodegradable waste. Non-biodegradable waste will be collected in separate bins and handed over to the AMC.
- Air and Noise: Dust suppression through water sprinkling and the use of silencers on construction machinery are planned during the building phase.
- Greenery: The plan includes planting 127 trees along the periphery, using local species such as Ashoka, Neem, and Jambu.
- Fire Safety: Facilities include a dedicated fire hydrant system, a 20,000-litre terrace tank for each building, fire extinguishers on each floor, and sprinklers in the basement parking areas.
Asopalav Green site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.2 acres, this one is smaller than 70% of them.
250 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nikol, Sabarmati, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Swarit Sky — environmental approval granted, 450 m away
- Swarit Sky — environmental approval granted, 550 m away
- Vedant Skyvilla — environmental approval granted, 550 m away
- Vedant Skyvilla — environmental approval granted, 550 m away
- Royal Revanta Gold — environmental approval granted, 650 m away
- The Celestial — environmental approval granted, 650 m away
- Atlantis — environmental approval granted, 650 m away
- Satved Heaven — environmental approval granted, 650 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.