What is Mahipatsinh Malubhai Parmar (Ordinary Sand Mine Block- 1)?
Mahipatsinh Malubhai Parmar (Ordinary Sand Mine Block- 1) is an approved mining project in Panshina, Limbdi, Surendranagar, Gujarat. The site covers 2.5 acres.
Who is building it?
The applicant is Parmar Mahipatsinh Malubhai.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Jan 2025), as of 27 Nov 2026.
Where is it?
In Panshina, Limbdi, Surendranagar, Gujarat.
How big is it?
It has a stated cost of ₹3.1 crore and a site of 2.5 acres.
When was it filed?
The application was filed on 10 Sept 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Jan 2025 |
| Application filed | 10 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Parmar Mahipatsinh Malubhai |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹3.1 crore |
| Village / locality | Panshina |
| Taluk / tehsil | Limbdi |
| District | Surendranagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-04706 |
In context
271 applications in Surendranagar since January 2022 are in the same category (Mining): 107 approved, 59 filed or under review, and 105 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.5 acres, this one is smaller than 97% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Panshina, Limbdi, Surendranagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Mahipatsinh Malubhai Parmar (Ordinary Sand Mine Block -2) — environmental approval granted, 1.8 km away
- 125 mm Dia. PE Gas Pipeline route Rajrajeshwardham Jhakhan To Ahmedabad… — forest land use approved, 2.7 km away
- Rajrishi Petroleum CNG Station Connectivity — forest land use approved, 13.1 km away
- Shi Dashrathbhai Vashrambhai Nandiyaniya — environmental approval granted, 22.1 km away
- Noc for 0.077 Ha. Entry/Exit Approach Road for Access to Petrol Pump on… — lapsed, 22.8 km away
- Seeking Prior Approval for Laying 400 Mm Dia. Drinking Water Pipeline on NH-51… — forest land use approved, 24.4 km away
- 765 kV D/c Halvad-Vataman Transmission Line (PVTL) — forest land use approved, 24.7 km away
- Shri Hakubhai Samantbhai Dhandhal — not approved, 25 km away
More from Parmar Mahipatsinh Malubhai in Surendranagar
- Mahipatsinh Malubhai Parmar (Ordinary Sand Mine Block -2) — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.