What is Mundra Thermal Power Station?
Mundra Thermal Power Station is a lapsed power project in Kandagara Mota, Mundra, Kachchh, Gujarat. The site covers 1,337.7 acres.
Who is building it?
The applicant is The Tata Power Co LTD.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Kandagara Mota, Mundra, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹18,000 crore and a site of 1,337.7 acres.
When was it filed?
The application was filed on 18 Mar 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 18 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | The Tata Power Co LTD |
| Land area | 1,337.7 acres (541.4 ha) |
| Project cost | ₹18,000 crore |
| Village / locality | Kandagara Mota |
| Taluk / tehsil | Mundra |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-05404 |
In context
75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 1,337.7 acres, this one is larger than 88% of them.
14 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kandagara Mota, Mundra, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to APSEZ Optimizes Mundra Port Waterfront in Kachchh for 514-Million-Tonne Capacity (10.3 km away).
Other projects nearby
- Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation… — lapsed, 1.6 km away
- Environmental & CRZ Clearance for Electronic Manufacturing Cluster (EMC) — returned to applicant, 1.9 km away
- "Workmen Accommodation – Plot A" Building Construction Project (Residential)… — environmental approval granted, 2.3 km away
- "Workmen Accommodation – Plot A" Building Construction Project (Residential)… — withdrawn, 2.3 km away
- "Workmen Accommodation – Plot A" Building Construction Project (Residential)… — environmental approval granted, 2.3 km away
- Residential Colony for Solar Manufacturing Business Plant/ Units at area… — initial checks, 2.7 km away
- Sea Water Intake of 350 MLD, Desalination Plant & Laying of 320 MLD Deep Sea… — coastal clearance granted, 2.9 km away
- Supporting facility for Worker/Employees -(Mundra Central Kitchen by Adani… — initial checks, 3 km away
All 25 The Tata Power Co projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.