Quick answers
What is this project?
Expansion in Limestone production capacity from 12.0 Million TPA to 26.5 Million TPA in Jadua Limestone Mine (ML Area - 1543.0958 ha) is a lapsed mining project in Jadva, Lakhpat, Kachchh, Gujarat. The site covers 3,813.1 acres.
Who is building it?
The applicant is Sanghi Industries Limited.
Has it been approved?
No. The application was lapsed on 14 Mar 2025, so it is no longer under consideration.
Where is it?
In Jadva, Lakhpat, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹115 crore and a site of 3,813.1 acres.
When was it filed?
The application was filed on 9 Aug 2024.
Project details
| Official title | Expansion in Limestone production capacity from 12.0 Million TPA to 26.5 Million TPA in Jadua Limestone Mine (ML Area - 1543.0958 ha) at Village - Jadua, Tehsil - Lakhpat, District - Kachchh (Gujarat). |
|---|---|
| Status | Lapsed |
| Status since | 14 Mar 2025 |
| Application filed | 9 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Sanghi Industries Limited |
| Land area | 3,813.1 acres (1,543.1 ha) |
| Project cost | ₹115 crore |
| Village / locality | Jadva |
| Taluk / tehsil | Lakhpat |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-05645 |
In context
1,132 applications in Kachchh since January 2022 are in the same category (Mining): 683 approved, 276 filed or under review, and 173 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 3,813.1 acres, this one is larger than 99% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Jadva, Lakhpat, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance for Jadua Limestone Mining Project of M/s… — lapsed, 0 m away
- Proposed Expansion of Clinker Plant Capacity (7.5 Million TPA to 17.5 Million… — cleared for impact study, 4.8 km away
- Proposed Expansion of Clinker Plant Capacity (7.5 Million TPA to 17.5 Million… — withdrawn, 4.8 km away
- Proposed Expansion of Clinker Plant Capacity (7.5 Million TPA to 17.5 Million… — environmental approval granted, 5.3 km away
- Diversion of 0.8330 Ha proposed Roadside Protected Forest land of Naredo to… — lapsed, 5.9 km away
- Motiber Silica Sand Mine (ML Area: 160.7582 Ha) with expansion in production… — more information requested, 6.8 km away
- Motiber Silica Sand Mine (ML Area: 160.7582 ha) with expansion in production… — under environmental review, 6.8 km away
- Expansion in Silica Sand production capacity from 0.315 million TPA to 2.84… — lapsed, 6.8 km away
More from Sanghi Industries Limited in Kachchh
- Proposed Expansion of Clinker Plant Capacity (7.5 Million TPA to 17.5 Million… — environmental approval granted
- Expansion of Sanghi Port at Kharo Creek, Kachchh district, Gujarat. — more information requested
- Motiber Silica Sand Mine (ML Area: 160.7582 ha) with expansion in production… — under environmental review
- Expansion in Silica Sand production capacity from 0.315 million TPA to 2.84… — lapsed
- Expansion of Sanghi Port at Kharo Creek, Kachchh District, Gujarat. — returned to applicant
- Proposed Expansion of Clinker Plant Capacity (7.5 Million TPA to 17.5 Million… — cleared for impact study
All 7 Sanghi Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.