Saffron Sky is an approved residential project in Delvada, Chorasi, Surat, Gujarat. It plans 196 units in 2 towers of up to 13 floors on 0.9 acres.
Who is building it?
The applicant is Prahladbhai Tribhovandas Patel.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 15 Jun 2025), as of 27 Nov 2026.
Where is it?
In Delvada, Chorasi, Surat, Gujarat.
How big is it?
It has a stated cost of ₹42.7 crore and a site of 0.9 acres.
When was it filed?
The application was filed on 17 Aug 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 15 Jun 2025 |
| Application filed | 17 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Prahladbhai Tribhovandas Patel |
| Use | Residential |
| Units | 196 |
| Towers | 2 |
| Floors (tallest) | 13 |
| Basements | 2 |
| Parking spaces | 214 |
| Land area | 3,800 m² |
| Built-up area | 26,329 m² (2,83,403 sq ft) |
| Plot area | 3,764 m² (40,515 sq ft) |
| Project cost | ₹42.7 crore |
| Village / locality | Delvada |
| Taluk / tehsil | Chorasi |
| District | Surat |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06717 |
What the filings say
What is planned
Saffron Sky is a proposed residential and commercial building project by Prahladbhai Tribhovandas Patel and others. According to the applicant's conceptual plan, the development will consist of two buildings divided into four blocks (A, B, C, and D). The project is designed with a ground floor plus 13 upper floors, supported by two basement levels and a hollow plinth for parking.
The project components include:
- Residential Units: 182 units across the blocks.
- Commercial Units: 14 shops located on the ground floor.
- Amenities: A clubhouse, children's play area, garden with a jogging track, and a common plot area of 376.50 square metres.
| Item | Detail |
|---|---|
| Total Plot Area | 3,763.80 sq. mt. |
| Total Built-up Area | 26,328.74 sq. mt. |
| FSI Area | 15,052.98 sq. mt. |
| Maximum Building Height | 44.98 m |
| Total Parking Provided | 5,336.96 sq. mt. (214 ECS) |
| Expected Population | 980 residents and 196 visitors |
Layout and design
The site layout features a 45-metre wide road on one side and an 18-metre wide proposed road on another. Block A is a standalone structure, while Blocks B, C, and D are interconnected. The ground floor is dedicated to commercial shops and building foyers, with residential units starting from the first floor.
Energy-efficient design measures include the use of aerated blocks (Cement + Fly Ash + Air mixture) to reduce heat stress, roof-top thermal insulation, and LED lighting in common areas. The applicant plans to install 185 solar panels with a capacity of 100 kW to power common area lighting and water pumps.
Water, power and access
The Surat Municipal Corporation (SMC) will be the primary source for water and drainage. During the operation phase, the total water requirement is estimated at 135 kilolitres per day (KLD). This includes 79.8 KLD of fresh water and 55.2 KLD of recycled water for flushing and gardening. A Sewage Treatment Plant (STP) using Moving Bed Biofilm Reactor (MBBR) technology with a capacity of 130 KLD will be installed to treat domestic wastewater.
Power will be supplied by Dakshin Gujarat Vij Company Limited (DGVCL) with a maximum demand of 1,000 kW. For emergency backup, three diesel generator sets of 125 kVA each are proposed. Access to the site will be provided through two gates, and the internal road width is planned at 7 metres.
Environmental safeguards
The applicant has budgeted ₹6.36 crore for the Environmental Management Plan. Key measures include:
- Waste Management: An Organic Waste Convertor (OWC) with a capacity of 200 kg/day will process kitchen waste into manure. Dry waste will be collected in bins and disposed of through the SMC door-to-door collection system.
- Rainwater Harvesting: One recharging bore well is proposed to recharge groundwater, with a collection system designed for a 1,599 cubic metre annual potential from the rooftop.
- Green Belt: A total of 400 square metres is designated for green space, where 95 trees of species such as Gul mohar, Limdo, and Jambu will be planted.
- Fire Safety: The project includes a wet riser system, external hydrants, sprinklers, and an underground fire water tank of 400,000 litres capacity. A fire safety plan approval was obtained from the Surat Municipal Corporation in August 2024.
Timeline
In an undertaking dated July 4, 2024, the applicant stated that no construction activity had started at the site. The project cost is estimated at ₹42.65 crore, which includes ₹1.90 crore for land and ₹30.75 crore for construction.
Saffron Sky site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
489 applications in Surat since January 2022 are in the same category (Buildings & townships): 376 approved, 79 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 0.9 acres, this one is smaller than 92% of them.
48 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Delvada, Chorasi, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Prayosha Gold — environmental approval granted, 50 m away
- Prayosha Jewel — more information requested, 100 m away
- Madhav Arista — withdrawn, 400 m away
- Madhav Arista — environmental approval granted, 400 m away
- Kailash Luxuria — environmental approval granted, 550 m away
- Prayosha Iconic — environmental approval granted, 700 m away
- Prayosha Crown and Prayosha Classic — environmental approval granted, 750 m away