Quick answers
What is this project?
Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW is an approved power project in Hajira, Chorasi, Surat, Gujarat.
Who is building it?
The applicant is Amns Power Hazira Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 15 Sept 2025), as of 27 Nov 2026.
Where is it?
In Hajira, Chorasi, Surat, Gujarat.
How big is it?
It has a stated cost of ₹2,178.8 crore.
When was it filed?
The application was filed on 1 Jul 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 15 Sept 2025 |
| Application filed | 1 Jul 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | Amns Power Hazira Limited |
| Project cost | ₹2,178.8 crore |
| Village / locality | Hajira |
| Taluk / tehsil | Chorasi |
| District | Surat |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-08482 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 1 Jul 2025 (this page) | Environmental approval granted | ₹2,178.8 crore | |
| Amendment filed 5 Jun 2024 | Environmental approval granted | ₹2,178.8 crore | |
| Expansion filed 13 Sept 2023 | Environmental approval granted | ₹2,178.8 crore | |
| Early planning filed 12 May 2023 | Cleared for impact study | ₹2,178.8 crore |
In context
39 applications in Surat since January 2022 are in the same category (Power): 22 approved, 13 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval.
40 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Hajira, Chorasi, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 0 m away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 0 m away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — cleared for impact study, 0 m away
- Name change to ArcelorMittal Nippon Steel India Private Limited – Diversion of… — lapsed, 300 m away
- Deep Draft Green Field Captive Port — lapsed, 550 m away
- Grant of Permission Required for laying of Drinking water pipeline, crossing /… — forest land use approved, 700 m away
- Diversion of 0.2596 ha. of PF land for laying of 90 mm dia. MDPE Gas Pipeline… — forest land use approved, 700 m away
- Expansion of Integrated Steel Plant from 15.6 to 28.4 MTPA Liquid Steel of… — more information requested, 850 m away
All 4 Amns Power Hazira projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.