Quick answers
What is this project?
Diversion of 0.2596 ha. of PF land for laying of 90 mm dia. MDPE Gas Pipeline for Hazira Village Connectivity Project, Taluka Choryashi District Surat is an approved pipeline project in Sunvali, Chorasi, Surat, Gujarat. The site covers 0.6 acres.
Who is building it?
The applicant is Gujarat Gas Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 18 Jul 2026), as of 27 Nov 2026.
Where is it?
In Sunvali, Chorasi, Surat, Gujarat.
How big is it?
It has a stated cost of ₹70 lakh; a site of 0.6 acres and 2,600 m² of forest land.
When was it filed?
The application was filed on 2 Nov 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 18 Jul 2026 |
| Application filed | 2 Nov 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Gujarat Gas Limited |
| Land area | 2,600 m² |
| Forest land | 2,600 m² |
| Project cost | ₹70 lakh |
| Village / locality | Sunvali |
| Taluk / tehsil | Chorasi |
| District | Surat |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14038 |
In context
36 applications in Surat since January 2022 are in the same category (Pipelines): 16 approved, 8 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 8 months from filing to approval. At 0.6 acres, this one is smaller than 52% of them.
44 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sunvali, Chorasi, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Grant of Permission Required for laying of Drinking water pipeline, crossing /… — forest land use approved, 50 m away
- Name change to ArcelorMittal Nippon Steel India Private Limited – Diversion of… — lapsed, 450 m away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 700 m away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 700 m away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 700 m away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — cleared for impact study, 700 m away
- Diversion of 2.087 Ha Reserved Forest Land for Hazira Port Railway… — initial checks, 750 m away
- Name change to ArcelorMittal Nippon Steel India Private Limited - Diversion of… — initial checks, 950 m away
More from Gujarat Gas Limited in Surat
- Diversion of 0.0337 Ha. of Protected Forest Land I.E. Road Side Strip… — in-principle approval, conditions pending
- Diversion of 0.0123 Ha. of PF Land for laying of 125 mm PE Pipeline Network to… — more information requested
- Diversion of 0.0020 ha. of PF land for laying of 6" Dia. NB Steel Gas Pipeline… — more information requested
- Gas Distribution Network in Mangrol Taluka & Surrounding Area (Mangrol Taluka… — lapsed
- : Diversion of 0. 0.9016 Ha. of Protected Forest Land for Laying 125 Mm Dia.… — lapsed
- Gas Distribution Network in Mandavi Taluka& Surrounding Area (D C Shah petrol… — more information requested
20 Gujarat Gas projects in Surat
All 289 Gujarat Gas projects across India