Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Feb 2026 |
| Application filed | 16 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | R a Developers |
| Use | Mixed use |
| Units | 574 |
| Towers | 11 |
| Floors (tallest) | 4 |
| Height | 17 m |
| Parking spaces | 859 |
| Land area | 2.9 acres (1.2 ha) |
| Built-up area | 32,181 m² (3,46,393 sq ft) |
| Plot area | 11,635 m² (1,25,238 sq ft) |
| Project cost | ₹63.9 crore |
| Village / locality | Changodar |
| Taluk / tehsil | Sanand |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-08762 |
What the filings say
What is planned
The applicant, R A Developers, proposes to construct a residential affordable housing project named "VRUNDAVAN-2" in Changodar. According to the conceptual master plan, the project consists of five residential buildings (Building-1 to Building-5) and a small sixth building (Building-6) for a society office.
The residential component comprises 552 units in total, plus 22 commercial units located on the ground floor of Building-1. The residential buildings are designed with a hollow plinth or stilt for parking, followed by five floors. The total built-up area is 32,181.40 square metres.
| Item | Detail |
|---|---|
| Total Units | 552 Residential + 22 Commercial |
| Building Height | 14.90 metres (5 floors) |
| Total Built-up Area | 32,181.40 square metres |
| FSI Area | 20,942.07 square metres |
| Common Plot Area | 1,192.72 square metres |
| Estimated Cost | ₹63.9 crore |
Layout and design
The site layout shows the five main blocks arranged around a central common plot. Building-1 is situated at the front near the entry, while Buildings 2, 3, 4, and 5 are positioned along the periphery. Internal access is provided by a 12-metre wide crossover road and 6-metre to 7.5-metre wide approach roads.
Building-1 (Block A) contains the commercial shops on the ground floor. Buildings 2, 3, 4, and 5 (Blocks B through K) are dedicated to residential units. Each residential block features lift facilities and staircases. The design includes a hollow plinth and stilt area specifically for parking and utility services.
Land and surroundings
The project is located on Survey No. 18 Paiki in Changodar village, Sanand. The total plot area is 12,074 square metres, of which 438.97 square metres is designated for road widening, leaving a net plot area of 11,635.03 square metres. The site is currently open land. The applicant states that the Moraiya railway station is approximately 500 metres away, and Ahmedabad Airport is about 25 km from the site.
Water, power and access
During the construction phase, water will be sourced from local tankers or the Ahmedabad Urban Development Authority (AUDA). For the operational phase, the applicant intends to obtain Narmada water supply from AUDA. Domestic sewage will be discharged into the AUDA drainage line.
Power requirements are estimated at 25 kW during construction and approximately 1.0 MW during operation, to be sourced from Uttar Gujarat Vij Company Limited (UGVCL). Access to the site is via the Lagu Village Road. The project includes a parking layout providing 4,102.20 square metres of residential parking and 396.85 square metres for commercial and visitor use.
Environmental safeguards
The applicant proposes several mitigation measures in the Environmental Management Plan:
- Rainwater Harvesting: Four percolation wells are planned to recharge ground aquifers.
- Greenbelt Development: A total of 302 trees are required to be planted on-site, covering approximately 10% of the plot area.
- Waste Management: Municipal solid waste will be segregated into dry and wet waste. Wet waste is intended to be composted in an organic waste converter for use as manure in the greenbelt.
- Energy Conservation: Use of LED lighting in common areas, solar lights for open spaces, and energy-efficient motors and pumps.
- Pollution Control: During construction, water sprinkling and tarpaulin covers will be used to control dust. D.G. sets will be equipped with acoustic enclosures to mitigate noise.
Vrundavan-2 site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 2.9 acres, this one is larger than 78% of them.
34 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Changodar, Sanand, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Siddhivinayak prime — initial checks, 400 m away
- Siddhivinayak Prime — withdrawn, 400 m away
- Siddhivinayak Prime — environmental approval granted, 400 m away
- Project by Acute Research PVT LTD — initial checks, 800 m away
- Expansion in Synthetic Organic Chemicals (Resin+ Laminate) Manufacturing Unit… — returned to applicant, 1.3 km away
- Expansion in Synthetic Organic Chemicals (Resin+ Laminate) Manufacturing Unit… — cleared for impact study, 1.3 km away
- Proposed Project for Manufacturing of Various Synthetic Organic Chemicals by… — initial checks, 1.3 km away
- Proposed Project for Manufacturing of Various Synthetic Organic Chemicals by… — cleared for impact study, 1.3 km away
About this information