What is Developing? Open the mapMap

Environmental approval grantedBuildings & townships · Surat, Gujarat

Sangini Lakewoods

Sangini Lakewoods is an approved residential project in Gaviyar, Majura, Surat, Gujarat. It plans 250 units in 8 towers of up to 13 floors on 3.2 acres. Its stated project cost is ₹117.8 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 30 Jan 2026).

See it on the live map All projects in Surat

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Sangini Lakewoods?

Sangini Lakewoods is an approved residential project in Gaviyar, Majura, Surat, Gujarat. It plans 250 units in 8 towers of up to 13 floors on 3.2 acres.

Who is building it?

The applicant is Vraj Developers.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 30 Jan 2026), as of 27 Nov 2026.

Where is it?

In Gaviyar, Majura, Surat, Gujarat.

How big is it?

It has a stated cost of ₹117.8 crore and a site of 3.2 acres.

When was it filed?

The application was filed on 30 Jan 2026.

Project details

StatusEnvironmental approval granted
Status since30 Jan 2026
Application filed30 Jan 2026
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantVraj Developers
UseResidential
Units250
Towers8
Floors (tallest)13
Basements2
Parking spaces581
Land area3.2 acres (1.3 ha)
Built-up area79,830 m² (8,59,282 sq ft)
Plot area12,912 m² (1,38,983 sq ft)
Project cost₹117.8 crore
Village / localityGaviyar
Taluk / tehsilMajura
DistrictSurat
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-09909

What the filings say

What is planned

The applicant, Vraj Developers, proposes to construct a new residential building project named Sangini Lakewoods in Gaviyar, Surat. The project report describes a development consisting of eight residential buildings (comprising nine blocks) with two basement levels, a hollow plinth, and 13 upper floors. The tallest building will reach a height of 44.96 metres.

The project will provide a total of 250 residential units. The built-up area is distributed across different building types as follows:

Amenities planned for the society include a clubhouse, children's play area, a garden with a jogging track, and an indoor games area with a gym and library.

Layout and design

The project is situated on a plot of 1.29 hectares (3.19 acres). The site layout includes internal roads with a width of 7 metres and a minimum open path of 7 metres around the buildings for fire tender access. The total proposed parking area is 18,359.48 sq. mt., providing space for 581 Equivalent Car Spaces (ECS). This includes 523 spaces in the basement and 58 spaces in the hollow plinth.

Energy conservation measures include the installation of 333 solar panels on the rooftops, expected to generate 180 kW of power. The applicant plans to use eco-friendly materials such as fly ash bricks, aerated blocks for wall partitions, and lead-free paints.

Water, power and access

The total water requirement for the project during the operation phase is estimated at 239 kilolitres per day (KLD). Fresh water of 139.4 KLD will be sourced from the Surat Municipal Corporation (SMC), while 99.6 KLD will be met through recycled water for flushing and gardening. A sewage treatment plant (STP) with a capacity of 230 KLD using Moving Bed Biofilm Reactor (MBBR) technology will be installed.

Electrical power will be supplied by Dakshin Gujarat Vij Company Limited (DGVCL), with a maximum demand of 1,800 kW. For emergency backup, the applicant proposes to install six silent diesel generator sets, each with a capacity of 225 kVA. The site is accessed via a 36-metre wide Development Plan (DP) road.

Environmental safeguards

The project includes a green belt area of 1,300 sq. mt., where 323 trees are planned to be planted, including species such as Gul mohar, Jambu, and Badam. For rainwater management, four recharging bore wells will be provided to recharge groundwater.

Solid waste management plans include an organic waste convertor with a capacity of 400 kg/day to process kitchen waste into manure. Inorganic waste will be collected in bins and disposed of through the SMC collection system. The budgetary provision for the Environmental Management Plan is ₹12.79 crore, covering the STP, air and noise pollution control, and solar energy systems.

ItemDetail
Total Plot Area12,912.12 sq. mt.
Total Built-up Area79,830.38 sq. mt.
Residential Units250
STP Capacity230 KLD
Solar Power Generation180 kW
Total Parking Spaces581 ECS
Green Belt Area1,300 sq. mt.

Sangini Lakewoods site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Sangini Lakewoods: Master layout plan: building blocks, internal roads, and common plot (preview)🔒 Sign in free to see it
Master layout plan: building blocks, internal roads, and common plot
Sangini Lakewoods: Detailed site plan with area statement and FSI calculations (preview)🔒 Sign in free to see it
Detailed site plan with area statement and FSI calculations
Sangini Lakewoods: Basement and ground floor parking layout (preview)🔒 Sign in free to see it
Basement and ground floor parking layout
Sangini Lakewoods: Satellite view of the project site boundaries (preview)🔒 Sign in free to see it
Satellite view of the project site boundaries

In context

489 applications in Surat since January 2022 are in the same category (Buildings & townships): 376 approved, 79 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 3.2 acres, this one is larger than 84% of them.

71 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Gaviyar, Majura, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.