Kelikunj Vedika 2

Kelikunj Vedika 2 is a proposed building project in Puna, Majura, Surat, Gujarat. The site covers 1.4 acres. Its stated project cost is ₹41.6 crore. As of 27 Nov 2026, its status is “Under environmental review” (since 17 Nov 2026).

See it on the live map All projects in Surat

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Kelikunj Vedika 2?

Kelikunj Vedika 2 is a proposed building project in Puna, Majura, Surat, Gujarat. The site covers 1.4 acres.

Who is building it?

The applicant is S.K.Enterprise.

Has it been approved?

Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.

Where is it?

In Puna, Majura, Surat, Gujarat.

How big is it?

It has a stated cost of ₹41.6 crore and a site of 1.4 acres.

When was it filed?

The application was filed on 4 Jun 2026.

Project details

StatusUnder environmental review
Status since17 Nov 2026
Application filed4 Jun 2026
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantS.K.Enterprise
Land area1.4 acres (0.6 ha)
Project cost₹41.6 crore
Village / localityPuna
Taluk / tehsilMajura
DistrictSurat
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-10691

What the filings say

What is planned

S.K.Enterprise proposes the construction of Kelikunj Vedika 2, a residential and commercial project in Puna, Surat. The applicant's project report describes a development consisting of four building blocks (A, B, C, and D) with a maximum height of 42.17 metres. The buildings are planned for a Ground + 11 floor configuration over a single basement level.

The project is designed to accommodate 183 residential units and 22 commercial shops. The total built-up area is planned at 24,508.17 square metres, with a Floor Space Index (FSI) area of 14,700.19 square metres.

Unit and Area Breakdown

ItemDetail
Total Residential Units183
Total Commercial Shops22
Total Built-up Area24,508.17 sq. mt.
Total FSI Area14,700.19 sq. mt.
Ground Coverage1,878.06 sq. mt.
Common Plot Area545.41 sq. mt.
Maximum Building Height42.17 metres
Proposed Parking Area6,407.61 sq. mt.

Layout and design

The master plan indicates that the four blocks are arranged around a central common plot (C.O.P.-1) of 545.41 square metres (0.13 acres). The ground floor is dedicated to both commercial and residential uses, with shops fronting the main approach. The typical floors from the second level upwards are primarily residential.

Parking is distributed across the basement, ground level, and hollow plinth areas. The basement level covers 4,860.82 square metres and is accessed via a ramp. The design includes mechanical ventilation for the basement area. The project also features a rooftop solar system with a capacity of 60 KW, requiring approximately 360 square metres of terrace space.

Land and surroundings

The project site occupies 0.55 hectares (1.36 acres) of land in Puna, Surat. The site is bounded by an 18.00-metre wide road. According to the land documents, the plot is situated on Final Plot numbers 80 and 81, corresponding to Block numbers 208 and 209. The surrounding area consists of other residential blocks and open plots.

Water, power and access

Water requirements will be met through the local municipal supply. For wastewater management, the applicant proposes an on-site Sewage Treatment Plant (STP) with a capacity of 125 kilolitres per day (KLD) using Membrane Bioreactor (MBR) technology. Treated sewage will be discharged into the Surat Municipal Corporation (SMC) drainage system.

Power will be sourced from the state grid, with Diesel Generator (DG) sets provided for emergency backup. Access to the site is provided via an 18.00-metre wide road, with internal approach roads of 6.00 metres and 6.71 metres width.

Environmental safeguards

The Environmental Management Plan (EMP) outlines several mitigation measures. For air quality, the applicant proposes dust mitigation during construction and the installation of stacks for DG sets. Noise control measures include acoustic enclosures for the DG sets, which will be located in the basement.

Rainwater harvesting is planned through two percolating wells. The green belt development plan includes planting 137 trees, such as Asopalav, Gulmohar, Palm, Badam, and Neem. The total green area, including lawns and tree cover, is planned at 852.39 square metres, representing 15% of the plot area. Solid waste will be managed using an automatic Organic Waste Converter (OWC) with a capacity of 200 kg per day.

Kelikunj Vedika 2 site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Kelikunj Vedika 2: Site layout: building blocks, common plot, and road access (preview)🔒 Sign in free to see it
Site layout: building blocks, common plot, and road access
Kelikunj Vedika 2: Parking plan: basement and ground level layouts (preview)🔒 Sign in free to see it
Parking plan: basement and ground level layouts
Kelikunj Vedika 2: Building sections: floor heights and basement ramp (preview)🔒 Sign in free to see it
Building sections: floor heights and basement ramp
Kelikunj Vedika 2: Front elevation of building blocks A and D (preview)🔒 Sign in free to see it
Front elevation of building blocks A and D

In context

489 applications in Surat since January 2022 are in the same category (Buildings & townships): 376 approved, 79 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.4 acres, this one is smaller than 60% of them.

125 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Puna, Majura, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.