What is this project?
Diversion of Protected Forest Land for Up-gradation to 2L PS including pre-construction activities from Km. 53.840 to 137.894 of NH-754K in the State of Gujarat, Kachchh District is a proposed road project in Dhordo, Bhuj, Kachchh, Gujarat. The site covers 110.6 acres.
Who is building it?
The applicant is Ministry of Road Transport & Highways.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Dhordo, Bhuj, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹459 crore; a site of 110.6 acres and 110.6 acres (44.8 ha) of forest land.
When was it filed?
The application was filed on 11 Sept 2024.
Project details
| Official title | Proposal for Diversion of Protected Forest Land for Up-gradation to 2L PS including pre-construction activities from Km. 53.840 to 137.894 of NH-754K in the State of Gujarat, Kachchh District |
|---|---|
| Status | More information requested |
| Status since | 1 Sept 2026 |
| Application filed | 11 Sept 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Ministry of Road Transport & Highways |
| Land area | 110.6 acres (44.8 ha) |
| Forest land | 110.6 acres (44.8 ha) |
| Project cost | ₹459 crore |
| Village / locality | Dhordo |
| Taluk / tehsil | Bhuj |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12032 |
In context
76 applications in Kachchh since January 2022 are in the same category (Roads & highways): 23 approved, 32 filed or under review, and 19 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 110.6 acres, this one is larger than 86% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dhordo, Bhuj, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest Land for Construction of 66 KV Overhead Transmission Line… — under forest review, 2.6 km away
- Diversion of Forest Land for Construction of 66 KV Over Headed Transmission Line — lapsed, 2.9 km away
- Diversion of 9.0039 ha Forest area for proposed 66 KV S/C line from Ext. 66 KV… — forest land use approved, 8 km away
- Diversion of Protected Forest Land for construction of Green Field By-Pass… — more information requested, 13.9 km away
- Diversion of Protected Forest Land for widening and strengthening of… — lapsed, 15.9 km away
- Archean Chemical Industries — initial checks, 17.3 km away
- Diversion of Kutch West Forest Division and Banngrass land Division Forest… — lapsed, 19.5 km away
- Diversion of 0.5647 Ha Proposed Bannigrass land Protected Forest land for… — forest land use approved, 20.3 km away