Quick answers
What is this project?
Diversion of Protected Forest Land for improvement and widening of Bhuj-Nakhatrana Road (SH-42) and development as High Speed Corridor is a proposed road project in Mirjapar, Bhuj, Kachchh, Gujarat. The site covers 134.7 acres.
Who is building it?
The applicant is Public Works Department.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Mirjapar, Bhuj, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹600 crore; a site of 134.7 acres and 134.7 acres (54.5 ha) of forest land.
When was it filed?
The application was filed on 23 Sept 2025.
Project details
| Official title | Diversion of Protected Forest Land for improvement and widening of Bhuj-Nakhatrana Road (SH-42) and development as High Speed Corridor in Kachchh District. |
|---|---|
| Status | More information requested |
| Status since | 29 Sept 2026 |
| Application filed | 23 Sept 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Public Works Department |
| Land area | 134.7 acres (54.5 ha) |
| Forest land | 134.7 acres (54.5 ha) |
| Project cost | ₹600 crore |
| Village / locality | Mirjapar |
| Taluk / tehsil | Bhuj |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12726 |
In context
76 applications in Kachchh since January 2022 are in the same category (Roads & highways): 23 approved, 32 filed or under review, and 19 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 134.7 acres, this one is larger than 92% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mirjapar, Bhuj, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 66kV UG Cable laying work for 66kV Deshalpar to Manjal line under KSY-II with… — forest land use approved, 4.8 km away
- Approaches of 4 Lane Road Over Bridges and other Misc. works in lieu of Level… — more information requested, 5.9 km away
- Shri Khalifa Imran Abdreman — environmental approval granted, 6.1 km away
- Kurbai Blacktrap Mine — under environmental review, 6.7 km away
- Diversion of Road-Side Protected Forest Land of Deshalpar-Naliya Road and… — in-principle approval, conditions pending, 8.9 km away
- 125 mm PE Gas Pipeline Connectivity from Swaminarayan Gurukul To Minerals &… — lapsed, 10.6 km away
- Deshalpar Telephone Exchg to Nakhatrana Telephone Exchg BSNL OFC Route — lapsed, 10.6 km away
- Joysar Kanaiya (Ajapar Dolerite Block- 1) — lapsed, 11.6 km away
More from Public Works Department in Kachchh
- Nakhatrana Bypass Road at Km. Ch.0/00 to 7/600 (Bhuj Lakhpat Road 6/500 to… — lapsed
- Widening Strengthening of Dayapar Subhashpar Pandhro Road, Lakhpat to… — under wildlife review
- Widening Strengthening of Dayapar Subhashpar Pandhro Road, Lakhpat to… — more information requested
- DIVERSION OF 28.5621 HA. in Sanctuary for Widening & Strengthening of… — application filed
- Diversion of Protected Forest Land for Widening of Kera - Naredi - Mothala… — more information requested
- Diversion of Protected Forest Land for Widening and Strengthening of Mundra to… — more information requested
19 Public Works Department, Gujarat projects in Kachchh
All 102 Public Works Department, Gujarat projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.