Quick answers
What is this project?
Permission of 0.0123 ha. Forest Land for laying proposed 66kV S/C 630 Sq. mm. (3+1) XPLE underground cable line from 66KV Hariyal S/S to Gantry of M/s Solex Energy Ltd passing through Kim - Mandvi State road in Ta. Mandvi & Dist. Surat is an approved power project in Tadkeshvar, Mandvi Surat, Surat, Gujarat. The site covers 0.2 acres.
Who is building it?
The applicant is Getco Bharuch.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 25 Aug 2026), as of 27 Nov 2026.
Where is it?
In Tadkeshvar, Mandvi Surat, Surat, Gujarat.
How big is it?
It has a stated cost of ₹1 crore; a site of 0.2 acres and 120 m² of forest land.
When was it filed?
The application was filed on 7 Oct 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 25 Aug 2026 |
| Application filed | 7 Oct 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Getco Bharuch |
| Land area | 900 m² |
| Forest land | 120 m² |
| Project cost | ₹1 crore |
| Village / locality | Tadkeshvar |
| Taluk / tehsil | Mandvi Surat |
| District | Surat |
| State | Gujarat |
| Location from | Site area on record |
| Our reference | WID-GJ-13214 |
In context
39 applications in Surat since January 2022 are in the same category (Power): 22 approved, 13 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 0.2 acres, this one is smaller than 100% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tadkeshvar, Mandvi Surat, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Industrial project by Enzyme Bioscience Private Limited — environmental approval granted, 450 m away
- TAJ PLYWOOD INDUSTRIES, Proposed addition of product Phenol Formaldehyde Resin… — environmental approval granted, 1 km away
- Taj Plywood Industries — more information requested, 1 km away
- Diversion of 17.9019 ha. PF Land for Widening and Construction of Toll-Plaza… — more information requested, 1.7 km away
- Diversion of Forest Land of 0.115hac. for Clearance for Laying of 66KV S/C… — more information requested, 3.1 km away
- Transfer of Environment Clearance (EC) from M/s. Jai India Alloys Industries… — under environmental review, 3.6 km away
- Project by King Chem Life Science Pvt. Ltd. — initial checks, 3.7 km away
- Industrial project by Oriilon Tectex PVT. LTD. — environmental approval granted, 4.2 km away
More from Getco Bharuch in Surat
- Permission of Forest Land for laying proposed 66kV D/C Partial Overhead line… — lapsed
- Permission of Forest Land for laying proposed 66kV D/C Partial Overhead line… — more information requested
- Laying proposed 66kV S/C 630 Sq. mm. (3+1) XPLE underground cable line from… — forest land use approved
- Grant Permission for Diversion of 0.175 Ha of Social Forest Land for Laying of… — lapsed
- Diversion of Forest Land of 0.115hac. for Clearance for Laying of 66KV S/C… — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.