What is this project?
Diversion of 0.5174 Ha. of Reserved Forest Land for grant Permission for laying Bharti Airtel Limited, Optical Fiber Cable (OFC) line in along the Panandhro, Naredi, Mudiya road of Ta.: Lakhpat, Dist.: Kachchh in State of Gujarat is a lapsed telecom project in Mudiya, Lakhpat, Kachchh, Gujarat. The site covers 1.3 acres.
Who is building it?
The applicant is Mohammad Irfan Shaikh.
Has it been approved?
No. The application was lapsed on 25 Apr 2025, so it is no longer under consideration.
Where is it?
In Mudiya, Lakhpat, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹10 lakh; a site of 1.3 acres and 1.3 acres (0.5 ha) of forest land.
When was it filed?
The application was filed on 20 Aug 2024.
Project details
| Official title | Proposal for Diversion of 0.5174 Ha. of Reserved Forest Land for grant Permission for laying Bharti Airtel Limited, Optical Fiber Cable (OFC) line in along the Panandhro, Naredi, Mudiya road of Ta.: Lakhpat, Dist.: Kachchh in State of Gujarat. |
|---|---|
| Status | Lapsed |
| Status since | 25 Apr 2025 |
| Application filed | 20 Aug 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Telecom |
| Applicant | Mohammad Irfan Shaikh |
| Land area | 1.3 acres (0.5 ha) |
| Forest land | 1.3 acres (0.5 ha) |
| Project cost | ₹10 lakh |
| Village / locality | Mudiya |
| Taluk / tehsil | Lakhpat |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-13294 |
In context
46 applications in Kachchh since January 2022 are in the same category (Telecom): 11 approved, 15 filed or under review, and 20 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 1.3 acres, this one is larger than 64% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mudiya, Lakhpat, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.5038 Ha. of Reserved Forest Land for grant Permission for… — lapsed, 0 m away
- DIVERSION OF 28.5621 HA. in Sanctuary for Widening & Strengthening of… — application filed, 2.2 km away
- Widening and strengthening of 1) Dayapar-Subhashpar-Pandhro Road, 2) Lakhpat… — application filed, 2.2 km away
- Widening Strengthening of Dayapar Subhashpar Pandhro Road, Lakhpat to… — under wildlife review, 3.3 km away
- Widening Strengthening of Dayapar Subhashpar Pandhro Road, Lakhpat to… — more information requested, 3.3 km away
- 11 KV Transmission for the Farmland Connection — more information requested, 3.7 km away
- Diversion of 0.3916 Ha. Forest Land for ( Out Side Nsws Area) Grant Permission… — under forest review, 3.8 km away
- Laying of 11 KV Transmission Line to Provide Electricity Connection to the… — lapsed, 4 km away
More from Mohammad Irfan Shaikh in Kachchh
- Proposed Roadside Protected Forest land of Naliya to Dumara Village — forest land use approved
- Proposed Road side Protected Forest land of Naliya to Dumara Village — lapsed
- Kothara Chokdi to Naliya Chokdi — lapsed
- Laying of Underground Optical Fiber to the Roadside Protected Forest Land of… — under forest review
- Diversion of 0.5038 Ha. of Reserved Forest Land for grant Permission for… — lapsed
- Laying of Underground Optical Fiber Cable From Naliya to Narayansarovar Road… — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.