Jetpur Project- Survey, Investigation, Design, Engineering, Procurement of Land, ROU, obtaining all Clearances including CRZ and Environmental Clearance, Construction Including 10 years Operation and Maintenance of Pipeline for Disposal of Industrial Effluent into Deep Sea from Industrial Areas of Jetpur.

Jetpur Project- Survey, Investigation, Design, Engineering, Procurement of Land, ROU, obtaining all Clearances including CRZ and Environmental Clearance, Construction Including 10 years Operation and Maintenance of Pipeline for Disposal of Industrial Effluent into Deep Sea from Industrial Areas of Jetpur is a lapsed pipeline project in Gosa, Porbandar, Gujarat. The site covers 2.1 acres. Its stated project cost is ₹675 crore. As of 27 Nov 2026, its status is “Lapsed” (since 19 Aug 2026).

See it on the live map All projects in Porbandar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Jetpur Project- Survey, Investigation, Design, Engineering, Procurement of Land, ROU, obtaining all Clearances including CRZ and Environmental Clearance, Construction Including 10 years Operation and Maintenance of Pipeline for Disposal of Industrial Effluent into Deep Sea from Industrial Areas of Jetpur is a lapsed pipeline project in Gosa, Porbandar, Gujarat. The site covers 2.1 acres.

Who is building it?

The applicant is Gujarat Water Infrastructure Limited.

Has it been approved?

No. The application was lapsed on 19 Aug 2026, so it is no longer under consideration.

Where is it?

In Gosa, Porbandar, Gujarat.

How big is it?

It has a stated cost of ₹675 crore; a site of 2.1 acres and 2.1 acres (0.8 ha) of forest land.

When was it filed?

The application was filed on 30 Dec 2025.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Jetpur Project- Survey, Investigation, Design, Engineering, Procurement of Land, ROU,…

Project details

StatusLapsed
Status since19 Aug 2026
Application filed30 Dec 2025
Approval soughtForest land use
Application typeNew project
SectorPipelines
ApplicantGujarat Water Infrastructure Limited
Land area2.1 acres (0.8 ha)
Forest land2.1 acres (0.8 ha)
Project cost₹675 crore
Village / localityGosa
Taluk / tehsilPorbandar
DistrictPorbandar
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-13893

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 19 Jul 2026Lapsed2.1 acres₹675 crore
New project filed 30 Dec 2025 (this page)Lapsed2.1 acres₹675 crore

In context

6 applications in Porbandar since January 2022 are in the same category (Pipelines): 3 approved, 0 filed or under review, and 3 withdrawn, lapsed or rejected.

2 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Gosa, Porbandar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Gujarat Water Infrastructure Limited in Porbandar

5 Gujarat Water Infrastructure projects in Porbandar
All 11 Gujarat Water Infrastructure projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.