What is 66kv kara-Mosali DC(6+1) Underground Cable line?
66kv kara-Mosali DC(6+1) Underground Cable line is an approved power project in Amnedara, Mangrol, Surat, Gujarat. The site covers 1.4 acres.
Who is building it?
The applicant is Nileshbhai G Patel.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 18 Aug 2026), as of 27 Nov 2026.
Where is it?
In Amnedara, Mangrol, Surat, Gujarat.
How big is it?
It has a stated cost of ₹33.6 crore; a site of 1.4 acres and 1.4 acres (0.6 ha) of forest land.
When was it filed?
The application was filed on 18 Dec 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 18 Aug 2026 |
| Application filed | 18 Dec 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Nileshbhai G Patel |
| Land area | 1.4 acres (0.6 ha) |
| Forest land | 1.4 acres (0.6 ha) |
| Project cost | ₹33.6 crore |
| Village / locality | Amnedara |
| Taluk / tehsil | Mangrol |
| District | Surat |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14184 |
In context
39 applications in Surat since January 2022 are in the same category (Power): 22 approved, 13 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 1.4 acres, this one is larger than 50% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Amnedara, Mangrol, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 34.6289 Ha. of Forest Land for Widening and Strengthening of… — under forest review, 3.3 km away
- Proposed 750 MW Lignite Power Plant (Unit-1, 2 & 3) by Gujarat Industries… — under environmental review, 6.7 km away
- Vastan Lignite Mine — returned to applicant, 7.2 km away
- Vastan Lignite Mine — cleared for impact study, 7.2 km away
- Shri Hareshbhai Khimajibhai Senjaliya — environmental approval granted, 9 km away
- Gauage Conversion (Narrow Gauge to broad Gauge) between Kosamba to Umarpada… — more information requested, 9.3 km away
- Chemical Fertilizer Manufacturing Plant at Sy. No. 577, Luvara, Mangrol,… — under environmental review, 9.8 km away
- Diversion of 5.5829 Ha of Protected Forest Land for widening of Moti Pardi –… — more information requested, 10.2 km away
More from Nileshbhai G Patel in Surat
- Diversion of Forest Land of 0.9708 Hac. for the Work of Laying of 1… — under forest review
- 66kv (400)Dinod-Kosamba-II D/C(6+1) UG Cable line — more information requested
- 66KV D/C(6+1) Underground Cable Line from 66KV FTP S/S to 66KV Kosamba-II S/S — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.