Quick answers
What is this project?
66 KV S/C line from Exist. Ghanghali-3 SS to Prop. M/s. M.G. Steel SS with 66 KV 1C X 630 Sq.mm (3+1) Under Ground Cable is an approved power project in Ghanghali, Sihor, Bhavnagar, Gujarat. The site covers 0.1 acres.
Who is building it?
The applicant is Gujarat Energy Transmission Corp LTD.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 12 Aug 2026), as of 27 Nov 2026.
Where is it?
In Ghanghali, Sihor, Bhavnagar, Gujarat.
How big is it?
It has a stated cost of ₹3.9 crore; a site of 0.1 acres and 260 m² of forest land.
When was it filed?
The application was filed on 15 Jun 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 12 Aug 2026 |
| Application filed | 15 Jun 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Gujarat Energy Transmission Corp LTD |
| Land area | 400 m² |
| Forest land | 260 m² |
| Project cost | ₹3.9 crore |
| Village / locality | Ghanghali |
| Taluk / tehsil | Sihor |
| District | Bhavnagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14311 |
In context
8 applications in Bhavnagar since January 2022 are in the same category (Power): 2 approved, 3 filed or under review, and 3 withdrawn, lapsed or rejected.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ghanghali, Sihor, Bhavnagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed regularization with expansion project by M/s. Prabodh Steel Pvt. Ltd.… — more information requested, 1.7 km away
- Proposed regularization with expansion project by M/s. Prabodh Steel Pvt. Ltd.… — returned to applicant, 1.7 km away
- Proposed regularization with expansion project by M/s. Prabodh Steel Pvt. Ltd.… — cleared for impact study, 1.7 km away
- Proposed Active Pharmaceutical Ingredient (API) manufacturing unit of M/s.… — environmental approval granted, 4.5 km away
- Proposed Active Pharmaceutical Ingredient (API) manufacturing unit of M/s.… — cleared for impact study, 4.5 km away
- 4" Steel Gas pipeline for DRS Installation at Shihor Ta: Shihor Dist: Bhavnagar — lapsed, 4.9 km away
- Diversion of 0.5280 Ha. Road Side Protected Forest Land for Construction of… — forest land use approved, 4.9 km away
- Construction & Improvement of Ghanghali Bhangadh Paliyad road — lapsed, 5 km away
More from Gujarat Energy Transmission Corp LTD in Bhavnagar
- 66kV D/C Panther tower line from 220kv Mota Asarana S/S to 66kV Babariyadhar… — in-principle approval, conditions pending
- 66kV D/C Panther Tower Line from 220kV Mota Asarana S/S to 66kV Babariyadhar… — lapsed
- LILO of both circuits of 220kV D/C Otha-GPPC line at Prop. 220kV Mota Asarana… — forest land use approved
- 66kV S/C (3+1) 630Sq.mm Underground Cable from 66kV Gariyadhar to 66kV Virdi… — lapsed
- 66KV S/C (3+1) 630Sq.mm Underground Cable from 66KV Sidsar Sub-station to 66KV… — forest land use approved
6 Gujarat Energy Transmission Corp projects in Bhavnagar
All 231 Gujarat Energy Transmission Corp projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.