| Official title | Proposed 30 KLPD Malt Spirit Distillery & Bottling Plant for IMFL/CL (60 Lacs cases Annually) along with 1.5 MW Co-generation Power Plant at Village Phandi Boriwala, Tehsil Paonta Sahib, District Sirmaur, Himachal Pradesh by M/s. ADS Spirits Private Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 12 Mar 2026 |
| Application filed | 22 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | ADS Spirits private limited |
| Land area | 25.7 acres (10.4 ha) |
| Project cost | ₹63 crore |
| Village / locality | Phandi Boriwala (161) |
| Taluk / tehsil | Paonta Sahib |
| District | Sirmaur |
| State | Himachal Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-HP-00375 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 22 Oct 2025 (this page) | Environmental approval granted | 25.7 acres | ₹63 crore |
| Early planning filed 20 Dec 2024 | Cleared for impact study | 25.7 acres | ₹63 crore |
In context
12 applications in Sirmaur since January 2022 are in the same category (Industry): 6 approved, 2 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 25.7 acres, this one is larger than 67% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Phandi Boriwala (161), Paonta Sahib, Sirmaur, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 30 KLPD Malt Spirit Distillery & Bottling Plant for IMFL/CL (60 Lacs… — cleared for impact study, 0 m away
- Extraction of Sand, Stone and Bajri from Sunkar River Khasra No.2/4 Measuring… — cleared for impact study, 2.6 km away
- Construction of Link Road From Kodewala to Bhatanwala Km. 0/0 to 5/0 — lapsed, 4.2 km away
- Application for Extension in the Validity of Environmental Clearance of Steel… — environmental approval granted, 4.6 km away
- Mobile Tower for providing Telecommunication Line/Facilities — lapsed, 4.8 km away
- Extraction of sand, stone, and bajri from Khasra No. 3/1, measuring 33-15… — environmental approval granted, 6.1 km away
- Proposed 2KLPD Malt/Spirit/Grain Spirit Plant by VKM Liquor LLP — environmental approval granted, 6.3 km away
- Proposed 2KLPD Malt/Spirit/Grain Spirit Plant by VKM Liquor LLP — cleared for impact study, 6.3 km away
All 3 ADS Spirits projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.