Project details
| Status | Forest land use approved |
|---|---|
| Status since | 15 Apr 2026 |
| Application filed | 7 May 2025 |
| Approval sought | Forest land use |
| Application type | Change of use |
| Sector | Water & irrigation |
| Applicant | Sjvn Limited |
| Land area | 1,007.7 acres (407.8 ha) |
| Forest land | 1.2 acres (0.5 ha) |
| Project cost | ₹2,475.4 crore |
| Village / locality | Jangal Drabala (44) |
| Taluk / tehsil | Sunni |
| District | Shimla |
| State | Himachal Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-HP-01999 |
In context
11 applications in Shimla since January 2022 are in the same category (Water & irrigation): 2 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. At 1,007.7 acres, this one is larger than 91% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jangal Drabala (44), Sunni, Shimla, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Link Road From Dgbr Road Pipltu to Pandoa Temple Km 0/00 to 2/100 , Gram… — lapsed, 2.8 km away
- C/O Rajiv Gandhi Day Boarding School — lapsed, 3.1 km away
- Extraction of stone from Khasra No.180/2, measuring an area 00-57-62 Hectares… — environmental approval granted, 3.9 km away
- Link Road From Dharogra Daloghatti to Kanda Lunu Km 0/00 to 2/700 — lapsed, 5.1 km away
- Installtion of Mobile Tower for providng Telecommunication Line/ Facilities — lapsed, 5.9 km away
- Extraction of Sand, Stone and bajri falling in Mauza/Mohal Bhoot, Tehsil… — environmental approval granted, 6 km away
- Mobile Tower to provide Telecommunication Line/Facility — lapsed, 6.9 km away
- Mobile Tower to provide Telecommunication Line/Facility — lapsed, 7.1 km away
More from Sjvn Limited in Shimla
- Sand, Bajri & Stone, Area Measuring 4.67 Hectares Falling in Mauza Neether,… — initial checks
- Luhri Hydro-Electric Project - I — under environmental review
- Slope Protection Works uphill of Village Narola, District Shimla. — forest land use approved
- 220 kV D/c single zebra transmission line from switchyard of 210 MW Luhri… — in-principle approval, conditions pending
5 Sjvn projects in Shimla
All 17 Sjvn projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.