What is this project?
Diversion of forest land for approach access to Proposed Site of private property of M/s RRITAM REALITY LLP along ODR Road (Bahalgarh to Dipalpur Road) at K.M. Stone - 00.815 (R.H.S.) of Village - Bahalgarh, Tehsil - Rai, District - Sonipat (HR) is an approved building project in Bahalgarh, Sonipat, Haryana. The site covers 5 acres.
Who is building it?
The applicant is Rritam Reality LLP.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 22 Jul 2026), as of 27 Nov 2026.
Where is it?
In Bahalgarh, Sonipat, Haryana.
How big is it?
It has a stated cost of ₹1.2 crore; a site of 5 acres and 80 m² of forest land.
When was it filed?
The application was filed on 18 Nov 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 22 Jul 2026 |
| Application filed | 18 Nov 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Rritam Reality LLP |
| Use | Other |
| Land area | 5 acres (2 ha) |
| Forest land | 80 m² |
| Project cost | ₹1.2 crore |
| Village / locality | Bahalgarh |
| Taluk / tehsil | Sonipat |
| District | Sonipat |
| State | Haryana |
| Location from | Site boundary on record |
| Our reference | WID-HR-01574 |
In context
95 applications in Sonipat since January 2022 are in the same category (Buildings & townships): 26 approved, 13 filed or under review, and 56 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 5 acres, this one is smaller than 61% of them.
38 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bahalgarh, Sonipat, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Manufacturing Capacity of Avtar Steel Limited Unit – IV, Village-… — lapsed, 750 m away
- Industrial project by M/s Lohia Alloys Ltd. at 41-2/5, Village-Joshi Chauhan… — more information requested, 1.2 km away
- GC, CRPF Camp Sonipat from 33kv Khewra Sub Station Under Sub Division… — forest land use approved, 1.4 km away
- Expansion of Manufacturing Capacity of Avtar Steel Limited Unit – B, Village -… — environmental approval granted, 1.7 km away
- Ashoka University- North Campus — environmental approval granted, 1.9 km away
- Institutional Project "Rishihood University" by M/s Rishihood Foundation — more information requested, 2 km away
- Environmental Clearance of Ashoka University North Campus, an institutional… — under environmental review, 2.1 km away
- Environmental Clearance of Ashoka University North Campus, an institutional… — cleared for impact study, 2.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.