| Status | Environmental approval granted |
|---|---|
| Status since | 2 May 2024 |
| Application filed | 12 Dec 2023 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | NTPC Limited (NTPC) |
| Land area | 11,601.6 acres (4,695 ha) |
| Project cost | ₹5,045 crore |
| Village / locality | Barkagaon |
| Taluk / tehsil | Barkagaon |
| District | Hazaribagh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00107 |
In context
105 applications in Hazaribagh since January 2022 are in the same category (Mining): 73 approved, 15 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 11,601.6 acres, this one is larger than 93% of them.
6 other mining leases have applied within 500 m of this site; together with this one they cover 64,215.4 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 12 mining leases have applied within 5 km.
Where it is
Barkagaon, Hazaribagh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Pakri Barwadih Coal Mining Project (West & East Quarry) from 15… — environmental approval granted, 0 m away
- Amendment in EC w.r.t. Amalgamation of Environmental Clearances of Pakri… — lapsed, 0 m away
- Transfer of Forest Clearance (1026.438 Ha) of Pakri Barwadih Coal mining… — more information requested, 0 m away
- Diversion of 11.212 Ha Forest Land, Earmarked for Safety Zone (In Addition to… — lapsed, 50 m away
- Amendment of Environment Clearance of Pakri Barwadih Coal Mining Project, NTPC… — environmental approval granted, 100 m away
- Amendment of Environment Clearance of Pakri Barwadih Coal Mining Project, NTPC… — environmental approval granted, 100 m away
- Amendment of Environment Clearance of Pakri Barwadih Coal Mining Project, NTPC… — environmental approval granted, 100 m away
- Pakri Barwadih Coal Mining Project of M/s NTPC Limited — withdrawn, 100 m away
More from NTPC Limited (NTPC) in Hazaribagh
- Expansion of Pakri Barwadih Coal Mining Project (West & East Quarry) from 15… — environmental approval granted
- Expansion of Pakri Barwadih Coal Mining Project (West & East Quarry) from 15… — returned to applicant
- North West Quarry of Pakri Barwadih opencast Coal Mine Project — environmental approval granted
- Amendment in EC w.r.t. Amalgamation of Environmental Clearances of Pakri… — lapsed
- Amendment of Environment Clearance of Pakri Barwadih Coal Mining Project, NTPC… — environmental approval granted
- Kerandari Coal Mining Project — environmental approval granted
38 NTPC projects in Hazaribagh