What is Developing? Open the mapMap

Cleared for impact studyIndustry · Purbi Singhbhum, Jharkhand

Enhancement of existing steel plant and legitimizing violation units for total production of 643,500 TPA Sponge Iron, 199,500 TPA Billets, 165,000 TPA Rolled products, 65,000 TPA Ferro alloys (Max) by Shah Sponge and Power Ltd

Enhancement of existing steel plant and legitimizing violation units for total production of 643,500 TPA Sponge Iron, 199,500 TPA Billets, 165,000 TPA Rolled products, 65,000 TPA Ferro alloys (Max) by Shah Sponge and Power Ltd is a proposed industrial project in Juri, Potka, Purbi Singhbhum, Jharkhand. The site covers 48.6 acres. Its stated project cost is ₹780.2 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 3 Nov 2023).

See it on the live map All projects in Purbi Singhbhum

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Enhancement of existing steel plant and legitimizing violation units for total production of 643,500 TPA Sponge Iron, 199,500 TPA Billets, 165,000 TPA Rolled products, 65,000 TPA Ferro alloys (Max) by Shah Sponge and Power Ltd is a proposed industrial project in Juri, Potka, Purbi Singhbhum, Jharkhand. The site covers 48.6 acres.

Who is building it?

The applicant is Shah Sponge & Power Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 3 Nov 2023), as of 27 Nov 2026.

Where is it?

In Juri, Potka, Purbi Singhbhum, Jharkhand.

How big is it?

It has a stated cost of ₹780.2 crore and a site of 48.6 acres.

When was it filed?

The application was filed on 24 Apr 2023.

Project details

Official titleEnhancement of existing steel plant and legitimizing violation units for total production of 643,500 TPA Sponge Iron, 199,500 TPA Billets, 165,000 TPA Rolled products, 65,000 TPA Ferro alloys (Max) along with 70 MW Captive Power Plant at Village: Juri, P.O. Hata, Dist: East Singhbhum, Jharkhand State by Shah Sponge and Power Ltd
StatusCleared for impact study
Status since3 Nov 2023
Application filed24 Apr 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantShah Sponge & Power Limited
Land area48.6 acres (19.7 ha)
Project cost₹780.2 crore
Village / localityJuri
Taluk / tehsilPotka
DistrictPurbi Singhbhum
StateJharkhand
Location fromSite boundary on record
Our referenceWID-JH-00480

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 12 Apr 2024Lapsed48.6 acres₹780.2 crore
Early planning filed 24 Apr 2023 (this page)Cleared for impact study48.6 acres₹780.2 crore

In context

25 applications in Purbi Singhbhum since January 2022 are in the same category (Industry): 17 approved, 4 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 48.6 acres, this one is smaller than 76% of them.

9 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Juri, Potka, Purbi Singhbhum, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.