Project details
| Official title | Proposed project for Expansion of Sponge Iron plant from 48000 TPA to 66000TPA with Captive Power Plant 10 MW, MS Billets Production from 8400 TPA to 1,88,100 TPA by installing 3x15 Ton & 1X12 Ton Induction furnaces with CCM (2x4/7), Re Rolling Mill for production of 1,65,000 MTPA and Slag crunching unit (4000TPA) by M/s Jai Durga Iron (P) Ltd. at Village- Telaiya, Ward No.-04, Jhumri Telaiya Municipality, Pargana- Gumo, Thana No.-244, District- Koderma, State- Jharkhand |
|---|---|
| Status | Lapsed |
| Status since | 26 May 2025 |
| Application filed | 4 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Jai Durga Iron Private Limited |
| Land area | 17.7 acres (7.2 ha) |
| Project cost | ₹85.4 crore |
| Village / locality | Jhumri Tilaiya |
| Taluk / tehsil | Koderma |
| District | Kodarma |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00727 |
In context
17 applications in Kodarma since January 2022 are in the same category (Industry): 14 approved, 2 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 17.7 acres, this one is larger than 88% of them.
15 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jhumri Tilaiya, Koderma, Kodarma, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of MS Billets production from 48,000TPA to 180,000TPA by 5x15 Ton… — returned to applicant, 50 m away
- Shifting of 132 KV Transmission Line (Koderma S/S to Koderma Receiving S/S)… — lapsed, 2.2 km away
- 132 KV D/C KTPS GSS to Gujhandi TSS — lapsed, 3.8 km away
- 132 KV D/C From KTPS GSS to Gajhandi TSS Transmission Line — more information requested, 3.9 km away
- Proposed project for Enhancement of MS Billet Production From 15,000 TPA to… — environmental approval granted, 4.5 km away
- Proposed project for Enhancement of MS Billet Production From 15,000 TPA to… — cleared for impact study, 4.5 km away
- Greenfield 100,000 TPA Coal Tar Distillation Plant for production of 54,000… — environmental approval granted, 4.6 km away
- Greenfield 100,000 TPA Coal Tar Distillation Plant for production of 54,000… — cleared for impact study, 4.6 km away
More from Jai Durga Iron Private Limited in Kodarma
- Expansion of MS Billets production from 48,000TPA to 180,000TPA by 5x15 Ton… — returned to applicant
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.