One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of DRI Plant from 0.128 to 0.1485 MTPA, Existing 15 MW AFBC and WHRB based CPP…
Project details
| Official title | Expansion of DRI Plant from 0.128 to 0.1485 MTPA, Existing 15 MW AFBC and WHRB based CPP and Addition of 3 X 15 T Induction Furnace, 1 X 2 Strands of Continuous Casting Machine and 1 X 400 TPD Rolling Mill with Total Capacity of 0.132 MTPA, (Project Area Expansion From 12.14 Ha to 13.26 Ha) in village Senegarha, Rabodh Panchayat, Block Dadi, District Hazaribagh (Jharkhand) of M/s Anindita Steels Limited |
|---|---|
| Status | More information requested |
| Status since | 4 Nov 2026 |
| Application filed | 10 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Anindita Steels Limited |
| Land area | 86.8 acres (35.1 ha) |
| Project cost | ₹192.1 crore |
| Village / locality | Senagara |
| Taluk / tehsil | Dadi |
| District | Hazaribagh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-01922 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 10 Sept 2026 (this page) | More information requested | 86.8 acres | ₹192.1 crore |
| Early planning filed 24 Dec 2024 | Cleared for impact study | 86.8 acres | ₹192.1 crore |
In context
14 applications in Hazaribagh since January 2022 are in the same category (Industry): 11 approved, 2 filed or under review, and 1 withdrawn, lapsed or rejected. At 86.8 acres, this one is larger than 86% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Senagara, Dadi, Hazaribagh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of DRI Plant from 0.128 to 0.1485 MTPA, Existing 15 MW AFBC and WHRB… — cleared for impact study, 0 m away
- Anindita Steels Limited (Expansion through addition of AFBC/CFBC and WHRB… — environmental approval granted, 50 m away
- Iron Ore Beneficiation Plant (RSIPL) — lapsed, 2.1 km away
- Iron Ore Beneficiation Plant (RSIPL) — more information requested, 2.2 km away
- Rabodih OCP Coal Mine — cleared for impact study, 3.3 km away
- Rabodih OCP Coal Mine — cleared for impact study, 3.3 km away
- Rabodih OCP Coal Mine — lapsed, 3.3 km away
- New Giddi 'C' — lapsed, 3.9 km away
More from Anindita Steels Limited in Hazaribagh
- Anindita Steels Limited (Expansion through addition of AFBC/CFBC and WHRB… — environmental approval granted
All 3 Anindita Steels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.