Project details
| Status | Lapsed |
|---|---|
| Status since | 4 Apr 2024 |
| Application filed | 28 Oct 2023 |
| Approval sought | Forest land use |
| Application type | Renewal |
| Sector | Mining |
| Applicant | Central Coalfields Limited |
| Land area | 892.4 acres (361.2 ha) |
| Forest land | 181.7 acres (73.6 ha) |
| Project cost | ₹18.4 crore |
| Village / locality | Dari (Ct) |
| Taluk / tehsil | Dadi |
| District | Hazaribagh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02568 |
In context
105 applications in Hazaribagh since January 2022 are in the same category (Mining): 73 approved, 15 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 892.4 acres, this one is smaller than 55% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Dari (Ct), Dadi, Hazaribagh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Iron Ore Beneficiation Plant (RSIPL) — more information requested, 1.7 km away
- Iron Ore Beneficiation Plant (RSIPL) — lapsed, 1.9 km away
- Amendment in EC of Giddi A OCP (Capacity: 1 MTPA, Area: 187.98 Ha) — environmental approval granted, 3.7 km away
- Expansion of DRI Plant from 0.128 to 0.1485 MTPA, Existing 15 MW AFBC and WHRB… — more information requested, 3.9 km away
- Expansion of DRI Plant from 0.128 to 0.1485 MTPA, Existing 15 MW AFBC and WHRB… — cleared for impact study, 3.9 km away
- Anindita Steels Limited (Expansion through addition of AFBC/CFBC and WHRB… — environmental approval granted, 3.9 km away
- Rabodih OCP Coal Mine — cleared for impact study, 5.7 km away
- Rabodih OCP Coal Mine — cleared for impact study, 5.7 km away
More from Central Coalfields Limited in Hazaribagh
- Chandragupt Opencast Coal Mine Project — environmental approval granted
- NORTH URIMARI OCP (PROJECT AREA-504.14 Ha, CAPACITY- 6.0 MTY) — environmental approval granted
- Amendment in EC of Giddi A OCP (Capacity: 1 MTPA, Area: 187.98 Ha) — environmental approval granted
- NORTH URIMARI OCP (PROJECT AREA-504.14 Ha, CAPACITY- 6.0 MTY) — returned to applicant
- NORTH URIMARI OCP (PROJECT AREA-504.14 Ha, CAPACITY- 6.0 MTY) — cleared for impact study
- Chandragupt Opencast Coal Mine Project — environmental approval granted
10 Central Coalfields projects in Hazaribagh
All 66 Central Coalfields projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.