What is Konar CHP?
Konar CHP is a proposed project in Gobindpur, Bermo, Bokaro, Jharkhand. The site covers 233.2 acres.
Who is building it?
The applicant is Central Coalfields Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Gobindpur, Bermo, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹250.2 crore; a site of 233.2 acres and 30.8 acres (12.5 ha) of forest land.
When was it filed?
The application was filed on 4 Oct 2025.
Project details
| Status | More information requested |
|---|---|
| Status since | 30 Oct 2026 |
| Application filed | 4 Oct 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Other |
| Applicant | Central Coalfields Limited |
| Land area | 233.2 acres (94.4 ha) |
| Forest land | 30.8 acres (12.5 ha) |
| Project cost | ₹250.2 crore |
| Village / locality | Gobindpur |
| Taluk / tehsil | Bermo |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02363 |
In context
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gobindpur, Bermo, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Jarangdih Opencast Coal Mine — under environmental review, 1.2 km away
- Expansion of Jarangdih Opencast Coal Mine — environmental approval granted, 1.2 km away
- Khetko - Chalkari Sand Ghat — environmental approval granted, 4 km away
- Khetko – Chalkari Sand Ghat — environmental approval granted, 4 km away
- Khetko – Chalkari Sand Ghat — cleared for impact study, 4 km away
- New Kathara Coking coal washery of 3 MPTA capacity — environmental approval granted, 5.2 km away
- New Kathara Coking coal washery of 3 MPTA capacity — withdrawn, 5.3 km away
- New Sawang Coking Coal Washery — environmental approval granted, 6.1 km away
More from Central Coalfields Limited in Bokaro
- Expansion of Jarangdih Opencast Coal Mine — under environmental review
- Kotre Basantpur Pachmo OCP (Project Area: 1011.87 Ha, Capacity: 5 MTY) — environmental approval granted
- Expansion of Karo Opencast Coal Mining Project — environmental approval granted
- New Sawang Coking Coal Washery — environmental approval granted
- Angwali Opencast Project — lapsed
- Amlo Expansion OCP — environmental approval granted
15 Central Coalfields projects in Bokaro
All 66 Central Coalfields projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.