Quick answers
What is this project?
Kotre Basantpur Pachmo OCP (Project Area: 1011.87 Ha, Capacity: 5 MTY) is an approved mining project in Pachmo, Gomia, Bokaro, Jharkhand. The site covers 2,500.4 acres.
Who is building it?
The applicant is Central Coalfields Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 19 Aug 2026), as of 27 Nov 2026.
Where is it?
In Pachmo, Gomia, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹625.4 crore and a site of 2,500.4 acres.
When was it filed?
The application was filed on 22 Jun 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 19 Aug 2026 |
| Application filed | 22 Jun 2026 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Mining |
| Applicant | Central Coalfields Limited |
| Land area | 2,500.4 acres (1,011.9 ha) |
| Project cost | ₹625.4 crore |
| Village / locality | Pachmo |
| Taluk / tehsil | Gomia |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02034 |
In context
93 applications in Bokaro since January 2022 are in the same category (Mining): 76 approved, 3 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 41 days from filing to approval. At 2,500.4 acres, this one is larger than 97% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Pachmo, Gomia, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Right of Way (ROW) for the 11kV High Tension Line from Hurdag (Tapping Point)… — lapsed, 1000 m away
- 220kV D/C TTPS - Hazaribagh Transmission Line — more information requested, 2.3 km away
- Choritand Tilaiya Coal Mine — more information requested, 6.6 km away
- Prospecting of coal within Lalgarh South Coal Mine under Bokaro Forest… — forest land use approved, 7.5 km away
- Prospecting of coal within Lalgarh South Coal Mine under Bokaro Forest… — lapsed, 7.5 km away
- Prospecting of coal in Lalgarh South Coal Mine of M/s Rungta Sons Pvt.Ltd.… — lapsed, 7.5 km away
- 4/6 Lane (Green Field) access control expressway from Varanasi to Kolkata… — more information requested, 11 km away
- Gangpur Stone Mines — environmental approval granted, 14.8 km away
More from Central Coalfields Limited in Bokaro
- Expansion of Jarangdih Opencast Coal Mine — under environmental review
- Expansion of Karo Opencast Coal Mining Project — environmental approval granted
- New Sawang Coking Coal Washery — environmental approval granted
- Konar CHP — more information requested
- Angwali Opencast Project — lapsed
- Amlo Expansion OCP — environmental approval granted
15 Central Coalfields projects in Bokaro
All 66 Central Coalfields projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.