Quick answers
What is Choritand Tilaiya Coal Mine?
Choritand Tilaiya Coal Mine is a proposed mining project in Dakasaram, Gomia, Bokaro, Jharkhand. The site covers 616.2 acres.
Who is building it?
The applicant is Rungta Metals Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Dakasaram, Gomia, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹243 crore; a site of 616.2 acres and 311.1 acres (125.9 ha) of forest land.
When was it filed?
The application was filed on 26 Aug 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 9 Sept 2026 |
| Application filed | 26 Aug 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Mining |
| Applicant | Rungta Metals Private Limited |
| Land area | 616.2 acres (249.4 ha) |
| Forest land | 311.1 acres (125.9 ha) |
| Project cost | ₹243 crore |
| Village / locality | Dakasaram |
| Taluk / tehsil | Gomia |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02426 |
In context
93 applications in Bokaro since January 2022 are in the same category (Mining): 76 approved, 3 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 41 days from filing to approval. At 616.2 acres, this one is larger than 85% of them.
No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.
Where it is
Dakasaram, Gomia, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Prospecting of coal in Lalgarh South Coal Mine of M/s Rungta Sons Pvt.Ltd.… — lapsed, 2.4 km away
- Prospecting of coal within Lalgarh South Coal Mine under Bokaro Forest… — forest land use approved, 2.4 km away
- Prospecting of coal within Lalgarh South Coal Mine under Bokaro Forest… — lapsed, 2.4 km away
- Kotre Basantpur Pachmo OCP (Project Area: 1011.87 Ha, Capacity: 5 MTY) — environmental approval granted, 6.6 km away
- Right of Way (ROW) for the 11kV High Tension Line from Hurdag (Tapping Point)… — lapsed, 7.3 km away
- Gangpur Stone Mines — environmental approval granted, 8.2 km away
- Chorgawan Stone Mine — environmental approval granted, 8.2 km away
- 220kV D/C TTPS - Hazaribagh Transmission Line — more information requested, 8.9 km away
All 4 Rungta Metals projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.