Forest Diversion in 36.94 ha area of logistic corridor of West Bokaro, Tata Steel Ltd is a proposed mining project in Sarubera, Mandu, Ramgarh, Jharkhand. The site covers 127.6 acres.
Who is building it?
The applicant is Tata Steel Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under forest review”, as of 27 Nov 2026.
Where is it?
In Sarubera, Mandu, Ramgarh, Jharkhand.
How big is it?
It has a stated cost of ₹12.4 crore; a site of 127.6 acres and 91.3 acres (36.9 ha) of forest land.
When was it filed?
The application was filed on 17 May 2026.
Project details
| Status | Under forest review |
|---|---|
| Status since | 6 Nov 2026 |
| Application filed | 17 May 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Mining |
| Applicant | Tata Steel Limited |
| Land area | 127.6 acres (51.7 ha) |
| Forest land | 91.3 acres (36.9 ha) |
| Project cost | ₹12.4 crore |
| Village / locality | Sarubera |
| Taluk / tehsil | Mandu |
| District | Ramgarh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02515 |
In context
59 applications in Ramgarh since January 2022 are in the same category (Mining): 39 approved, 7 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 42 days from filing to approval. At 127.6 acres, this one is larger than 61% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 396.9 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 4 mining leases have applied within 5 km.
Where it is
Sarubera, Mandu, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- West Bokaro Coking Coal Washery of 10 MTPA Raw coal throughput in an area of… — lapsed, 200 m away
- Change in Land Use Over 9.8866 Ha Diverted Forest Land — more information requested, 950 m away
- West Bokaro NOPR Township Project of Tata Steel Limited — environmental approval granted, 3.6 km away
- Expansion of West Bokaro Opencast Mine — withdrawn, 4.5 km away
- Laiyo Sand Deposit (area 0.08 ha) — under environmental review, 5 km away
- 220 KV transmission line to M/S Tata Steel Ltd. at Vill: Ghatotand, Plot 165… — lapsed, 5.7 km away
- Kedla Opencast Project — environmental approval granted, 5.9 km away
- PUNDI OPENCAST PROJECT (Area: 774.26 Ha/ Capacity: 5.00 MTPA) — lapsed, 6.1 km away
More from Tata Steel Limited in Ramgarh
- Expansion of West Bokaro Opencast Mine — withdrawn
- West Bokaro NOPR Township Project of Tata Steel Limited — environmental approval granted
- Change in Land Use Over 9.8866 Ha Diverted Forest Land — more information requested
- West Bokaro Coking Coal Washery of 10 MTPA Raw coal throughput in an area of… — lapsed