Quick answers
What is 132 Kv D/C 3-Phase Gola-Petarwar Transmission Line?
132 Kv D/C 3-Phase Gola-Petarwar Transmission Line is a proposed power project in Bhubhui, Gola, Ramgarh, Jharkhand. The site covers 195.5 acres.
Who is building it?
The applicant is Dhanbad Tc Jusnl.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Bhubhui, Gola, Ramgarh, Jharkhand.
How big is it?
It has a stated cost of ₹17.9 crore; a site of 195.5 acres and 78.5 acres (31.7 ha) of forest land.
When was it filed?
The application was filed on 18 Nov 2023.
Project details
| Status | More information requested |
|---|---|
| Status since | 23 Apr 2026 |
| Application filed | 18 Nov 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Dhanbad Tc Jusnl |
| Land area | 195.5 acres (79.1 ha) |
| Forest land | 78.5 acres (31.7 ha) |
| Project cost | ₹17.9 crore |
| Village / locality | Bhubhui |
| Taluk / tehsil | Gola |
| District | Ramgarh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02607 |
In context
13 applications in Ramgarh since January 2022 are in the same category (Power): 3 approved, 6 filed or under review, and 4 withdrawn, lapsed or rejected. At 195.5 acres, this one is smaller than 75% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhubhui, Gola, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bhuinya Sagatu - Bamhan Sagatu Stone Deposit — environmental approval granted, 2.8 km away
- Hesapora Sand Deposit — lapsed, 6 km away
- Hesapora Sand Deposit — under environmental review, 6 km away
- Rola Stone Deposit (Area - 2.812 ha) — environmental approval granted, 7.5 km away
- Change in Land Use of Rajrappa Ocp — lapsed, 11.8 km away
- Rajrappa Coal Washery — environmental approval granted, 12 km away
- Expansion of the existing 28692 TPA MS Billets plant for final production of… — under environmental review, 12.2 km away
- Expansion of the existing steel plant for final production of 1,98,000 TPA MS… — withdrawn, 12.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.