Expansion of the existing steel plant for final production of 1,98,000 TPA MS Billets, 194000 TPA Rolled product, and 36000 TPA Slag Crusher by M/s VANANCHAL CONCAST PRIVATE LIMITED

Expansion of the existing steel plant for final production of 1,98,000 TPA MS Billets, 194000 TPA Rolled product, and 36000 TPA Slag Crusher by M/s VANANCHAL CONCAST PRIVATE LIMITED is a withdrawn industrial project in Jamuna, Gola, Ramgarh, Jharkhand. The site covers 7.3 acres. Its stated project cost is ₹165.5 crore. As of 27 Nov 2026, its status is “Withdrawn” (since 16 Oct 2026).

See it on the live map All projects in Ramgarh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of the existing steel plant for final production of 1,98,000 TPA MS Billets, 194000 TPA Rolled product, and 36000 TPA Slag Crusher by M/s VANANCHAL CONCAST PRIVATE LIMITED is a withdrawn industrial project in Jamuna, Gola, Ramgarh, Jharkhand. The site covers 7.3 acres.

Who is building it?

The applicant is Vananchal Concast Private Limited.

Has it been approved?

No. The application was withdrawn on 16 Oct 2026, so it is no longer under consideration.

Where is it?

In Jamuna, Gola, Ramgarh, Jharkhand.

How big is it?

It has a stated cost of ₹165.5 crore and a site of 7.3 acres.

When was it filed?

The application was filed on 16 Oct 2026.

Project details

Official titleExpansion of the existing steel plant for final production of 1,98,000 TPA MS Billets, 194000 TPA Rolled product, and 36000 TPA Slag Crusher along with allied facilities at Mauza – Bantara, PS- Gola, Dist. – Ramgarh, Jharkhand by M/s VANANCHAL CONCAST PRIVATE LIMITED
StatusWithdrawn
Status since16 Oct 2026
Application filed16 Oct 2026
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantVananchal Concast Private Limited
Land area7.3 acres (3 ha)
Project cost₹165.5 crore
Village / localityJamuna
Taluk / tehsilGola
DistrictRamgarh
StateJharkhand
Location fromSite boundary on record
Our referenceWID-JH-02141

In context

30 applications in Ramgarh since January 2022 are in the same category (Industry): 12 approved, 10 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 31 days from filing to approval. At 7.3 acres, this one is smaller than 83% of them.

3 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Jamuna, Gola, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.