What is this project?
Transmission system for evacuation of power from Pakal Dul (1000 MW), Kiru (624 MW) and Kwar (540 MW) HEPs of CVPPL is an approved power project in Pochhal, Kishtwar, Jammu and Kashmir. The site covers 0.1 acres.
Who is building it?
The applicant is Chenab Valley Power Projects Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 21 Apr 2026), as of 27 Nov 2026.
Where is it?
In Pochhal, Kishtwar, Jammu and Kashmir.
How big is it?
It has a site of 0.1 acres and 171.4 acres (69.4 ha) of forest land.
When was it filed?
The application was filed on 12 Sept 2024.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 21 Apr 2026 |
| Application filed | 12 Sept 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Chenab Valley Power Projects Limited |
| Land area | 300 m² |
| Forest land | 171.4 acres (69.4 ha) |
| Village / locality | Pochhal |
| Taluk / tehsil | Kishtwar |
| District | Kishtwar |
| State | Jammu and Kashmir |
| Location from | Site boundary on record |
| Our reference | WID-JK-01045 |
In context
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Pochhal, Kishtwar, Jammu and Kashmir. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- L052-(Link Road) Pallan to Peedal via Wani — more information requested, 2.2 km away
- L052-(Link Road) Pallan to Peedal via Wani — lapsed, 2.2 km away
- WSS Tikri Trigam — forest land use approved, 2.3 km away
- WSS Semina — forest land use approved, 3.6 km away
- WSS Semina — lapsed, 3.6 km away
- WSS Ayar — forest land use approved, 3.7 km away
- WSS Shandri — forest land use approved, 4 km away
- Link Road From Km 8th of Hsd Ji Road to Kunja Via Galigad — lapsed, 4.1 km away
More from Chenab Valley Power Projects Limited in Kishtwar
- Kirthai-II Hydroelectric Project — cleared for impact study
- FC of Downstream Quarry for Dam of Pakal Dul HEP — lapsed
- Kirthai-II Hydroelectric Project — more information requested
- Pakal Dul HE Project Kishtwar J&K — lapsed
All 6 Chenab Valley Power Projects projects across India