Quick answers
What is Pakal Dul HE Project Kishtwar J&K?
Pakal Dul HE Project Kishtwar J&K is a lapsed project in Lopara, Marwah, Kishtwar, Jammu and Kashmir. The site covers 28 acres.
Who is building it?
The applicant is Chenab Valley Power Projects Limited.
Has it been approved?
No. The application was lapsed on 16 Apr 2026, so it is no longer under consideration.
Where is it?
In Lopara, Marwah, Kishtwar, Jammu and Kashmir.
How big is it?
It has a stated cost of ₹12,670 crore; a site of 28 acres and 28 acres (11.3 ha) of forest land.
When was it filed?
The application was filed on 26 Jun 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 16 Apr 2026 |
| Application filed | 26 Jun 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Other |
| Applicant | Chenab Valley Power Projects Limited |
| Land area | 28 acres (11.3 ha) |
| Forest land | 28 acres (11.3 ha) |
| Project cost | ₹12,670 crore |
| Village / locality | Lopara |
| Taluk / tehsil | Marwah |
| District | Kishtwar |
| State | Jammu and Kashmir |
| Location from | Site boundary on record |
| Our reference | WID-JK-02263 |
In context
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Lopara, Marwah, Kishtwar, Jammu and Kashmir. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- WSS Lopara Lift — forest land use approved, 2.2 km away
- FC of Downstream Quarry for Dam of Pakal Dul HEP — lapsed, 3.1 km away
- WSS Tander Sounder and Kalnoo — forest land use approved, 4 km away
- WSS Sounder Bungam Sounder and Loharana — forest land use approved, 4.3 km away
- Water Supply Scheme Janakpur — forest land use approved, 5.4 km away
- WSS Troungie — forest land use approved, 5.8 km away
- WSS Pinjrari Ikhala — forest land use approved, 5.8 km away
- WSS Cheerji — forest land use approved, 7.2 km away
More from Chenab Valley Power Projects Limited in Kishtwar
- Kirthai-II Hydroelectric Project — cleared for impact study
- FC of Downstream Quarry for Dam of Pakal Dul HEP — lapsed
- Kirthai-II Hydroelectric Project — more information requested
- Transmission system for evacuation of power from Pakal Dul (1000 MW), Kiru… — forest land use approved
All 6 Chenab Valley Power Projects projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.