What is this project?
Amendment to the Environmental Clearance Issued for Expanding the Sugar Plant, Co-Generation Capacity, and Establishing a New Distillery to Produce Ethanol Using Multi-Feedstock, With Establishing a Captive Power Plant for the Distillery by M/S. Sri Sai Basava Sugars Limited (Formerly Known As M/S. Manali Sugars Limited) is an approved industrial project in Malaghan, Almel, Vijayapura, Karnataka. The site covers 102.3 acres.
Who is building it?
The applicant is Sri Sai Basava Sugars Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 4 Nov 2024), as of 27 Nov 2026.
Where is it?
In Malaghan, Almel, Vijayapura, Karnataka.
How big is it?
It has a stated cost of ₹527.3 crore and a site of 102.3 acres.
When was it filed?
The application was filed on 13 Aug 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 4 Nov 2024 |
| Application filed | 13 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Sri Sai Basava Sugars Limited |
| Land area | 102.3 acres (41.4 ha) |
| Project cost | ₹527.3 crore |
| Village / locality | Malaghan |
| Taluk / tehsil | Almel |
| District | Vijayapura |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01876 |
In context
37 applications in Vijayapura since January 2022 are in the same category (Industry): 20 approved, 8 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 102.3 acres, this one is smaller than 73% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Malaghan, Almel, Vijayapura, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed, 0 m away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn, 0 m away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn, 0 m away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn, 0 m away
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed, 0 m away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — lapsed, 0 m away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — environmental approval granted, 0 m away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — environmental approval granted, 0 m away
More from Sri Sai Basava Sugars Limited in Vijayapura
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.