One of 2 filings for this project. The project's main page, with every filing and where each stands: Building Stone Quarry
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 2 Apr 2026 |
| Application filed | 14 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Moideen a |
| Land area | 3 acres (1.2 ha) |
| Project cost | ₹40 lakh |
| Village / locality | Amaradevaragudda |
| Taluk / tehsil | Kudligi |
| District | Vijayanagar |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-03170 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 14 Nov 2025 (this page) | Environmental approval granted | 3 acres | ₹40 lakh |
| Ownership transfer filed 14 Nov 2025 | Environmental approval granted | 6 acres | ₹60 lakh |
In context
167 applications in Vijayanagar since January 2022 are in the same category (Mining): 81 approved, 30 filed or under review, and 56 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3 acres, this one is smaller than 68% of them.
No other mining lease on record is within 500 m of this site; 3 have applied within 5 km.
Where it is
Amaradevaragudda, Kudligi, Vijayanagar, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building Stone Quarry — environmental approval granted, 100 m away
- Building Stone Quarry of Bangari Hanumantha — environmental approval granted, 650 m away
- Diversion of forest land in Somalapura Reserve Forest in respect of M/s MSPL… — forest land use approved, 3.2 km away
- Building Stone Quarry (M-Sand) — more information requested, 3.9 km away
- Building Stone (M-Sand) Quarry — initial checks, 4.8 km away
- Building Stone Quarry by Sri. M. Maresh — environmental approval granted, 10.7 km away
- 33kv Interconnecting Underground Transmission line for 600MW Wind Power Project — decision issued, 12.9 km away
- Building Stone Quarry — lapsed, 14.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.