Proposed expansion of Sugarcane crushing capacity from existing 12000 TCD to 18000 TCD by M/s. Shri Prabhulingeshwar Sugars and Chemicals Ltd is a lapsed industrial project in Siddapur, Jamkhandi, Bagalkote, Karnataka. The site covers 110 acres. Its stated project cost is ₹532.6 crore. As of 27 Nov 2026, its status is “Lapsed” (since 13 Sept 2025).

See it on the live map All projects in Bagalkote

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Proposed expansion of Sugarcane crushing capacity from existing 12000 TCD to 18000 TCD by M/s. Shri Prabhulingeshwar Sugars and Chemicals Ltd is a lapsed industrial project in Siddapur, Jamkhandi, Bagalkote, Karnataka. The site covers 110 acres.

Who is building it?

The applicant is Shri Prabhulingeshwar Sugars and Chemicals Limited.

Has it been approved?

No. The application was lapsed on 13 Sept 2025, so it is no longer under consideration.

Where is it?

In Siddapur, Jamkhandi, Bagalkote, Karnataka.

How big is it?

It has a stated cost of ₹532.6 crore and a site of 110 acres.

When was it filed?

The application was filed on 27 May 2025.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed expansion of Sugarcane crushing capacity from existing 12000 TCD to 18000 TCD…

Project details

StatusLapsed
Status since13 Sept 2025
Application filed27 May 2025
Approval soughtEnvironmental approval
Application typeExpansion
SectorIndustry
ApplicantShri Prabhulingeshwar Sugars and Chemicals Limited
Land area110 acres (44.5 ha)
Project cost₹532.6 crore
Village / localitySiddapur
Taluk / tehsilJamkhandi
DistrictBagalkote
StateKarnataka
Location fromSite boundary on record
Our referenceWID-KA-04050

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 27 May 2025 (this page)Lapsed110 acres₹532.6 crore
Early planning filed 23 Jan 2024Cleared for impact study110 acres₹532.6 crore

In context

61 applications in Bagalkote since January 2022 are in the same category (Industry): 39 approved, 11 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 110 acres, this one is larger than 70% of them.

4 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Siddapur, Jamkhandi, Bagalkote, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.