Quick answers
What is this project?
Production of Rs/Ena/Ethanol Using Multi Feedstock B/C Heavy Molasses/Sugar Syrup/Grain in the Existing Distillery of 400 Klpd Capacity by M/S. Trualt Bioenergy Limited - Unit 3 is a proposed industrial project in Kallapur, Badami, Bagalkote, Karnataka. The site covers 17.6 acres.
Who is building it?
The applicant is TRUALT BIOENERGY LIMITED - Unit 3.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Kallapur, Badami, Bagalkote, Karnataka.
How big is it?
It has a stated cost of ₹235.9 crore and a site of 17.6 acres.
When was it filed?
The application was filed on 26 May 2026.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Production of Rs/Ena/Ethanol Using Multi Feedstock B/C Heavy Molasses/Sugar Syrup/Grain…
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 17 Jul 2026 |
| Application filed | 26 May 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | TRUALT BIOENERGY LIMITED - Unit 3 |
| Land area | 17.6 acres (7.1 ha) |
| Project cost | ₹235.9 crore |
| Village / locality | Kallapur |
| Taluk / tehsil | Badami |
| District | Bagalkote |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-05190 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 10 Aug 2026 | More information requested | 17.6 acres | ₹235.9 crore |
| Expansion filed 26 May 2026 (this page) | Returned to applicant | 17.6 acres | ₹235.9 crore |
| Early planning filed 15 Mar 2024 | Cleared for impact study | 17.6 acres | ₹235.9 crore |
In context
61 applications in Bagalkote since January 2022 are in the same category (Industry): 39 approved, 11 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 17.6 acres, this one is smaller than 97% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kallapur, Badami, Bagalkote, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Production of Rs/Ena/Ethanol Using Multi Feedstock B/C Heavy Molasses/Sugar… — more information requested, 0 m away
- Production of Rs/Ena/Ethanol Using Multi Feedstock B/C Heavy Molasses/Sugar… — cleared for impact study, 0 m away
- Transfer of EC for 'Expansion of sugarcane crushing capacity from 5,000 TCD to… — environmental approval granted, 400 m away
- Request for transfer/change of name in the Environmental Clearances granted to… — environmental approval granted, 450 m away
- Ordinary Sand Mining — environmental approval granted, 6 km away
- "Ordinary Sand Mining" of Sri. Sharanagouda P Goudar — environmental approval granted, 6.3 km away
- Mining project by M/s. Shiva Minerals and Traders — environmental approval granted, 7.1 km away
- Sri Sharanabasava V. Nagur — environmental approval granted, 7.3 km away
All 3 TRUALT BIOENERGY LIMITED projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.