One of 3 filings for this project. The project's main page, with every filing and where each stands: Narihalla PSP (300MW)
Project details
| Status | Lapsed |
|---|---|
| Status since | 12 May 2024 |
| Application filed | 23 Jan 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Other |
| Applicant | Jsw Energy Psp Three Limited |
| Land area | 745.8 acres (301.8 ha) |
| Forest land | 98.1 acres (39.7 ha) |
| Project cost | ₹1,590 crore |
| Village / locality | Taranagar |
| Taluk / tehsil | Sandur |
| District | Ballari |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-06401 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 23 Jan 2024 (this page) | Lapsed | 745.8 acres | ₹1,590 crore |
| New project filed 26 Apr 2023 | Lapsed | 745.8 acres | ₹1,590 crore |
| Early planning filed 23 Mar 2023 | Cleared for impact study | 745.8 acres | ₹1,590 crore |
In context
7 applications in Ballari since January 2022 are in the same category (Other): 0 approved, 4 filed or under review, and 3 withdrawn, lapsed or rejected.
23 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Taranagar, Sandur, Ballari, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Narihalla PSP (300MW) — lapsed, 0 m away
- Narihalla PSP (300MW) — cleared for impact study, 0 m away
- Proposed Narihalla Pumped Storage Project (300 MW) by M/s. JSW PSP Three Limited — cleared for impact study, 400 m away
- SL No 12, Donimalai Range, Sandur,Ballari — more information requested, 2.6 km away
- Diversion of forestland over an extent of 1.123 ha. area for Pipe Conveyor… — lapsed, 2.9 km away
- Re-Diversion of diverted forest land over an extent of 1.994 Ha w.r.t Pipe… — in-principle approval, conditions pending, 3 km away
- Re-diversion of forestland over an extent of 0.14 ha. area in favour of JSW… — lapsed, 3 km away
- Diversion of forestland over an extent of 2.781 ha area for pipe conveyor from… — in-principle approval, conditions pending, 3 km away
More from Jsw Energy Psp Three Limited in Ballari
- Proposed Narihalla Pumped Storage Project (300 MW) by M/s. JSW PSP Three Limited — cleared for impact study
All 4 Jsw Energy Psp Three projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.