One of 2 filings for this project. The project's main page, with every filing and where each stands: Diversion of 0.1066 Ha of Wild sanctuary protected land for laying 132/66kV Intermittent…
Project details
| Official title | Diversion of 0.1066 Ha of Wild sanctuary protected land for laying 132/66kV Intermittent UG cable in Cheelandavadi Village state Forest and Cauvery Wildlife Sanctuary Protected area Survey 01 in Uyyamballi Hobali and diversion of 1.0504 Ha of Minor Forest area in Uyyamballi Village Sy No: 147 & 194 , Kanakapura Taluk, Ramangara District for construction of 132/66kV Overhead line total 1.1570Ha of Forest land from existing 66/11kV Doddalahalli station to proposed 66/11kV Hegganur substation |
|---|---|
| Status | Initial checks |
| Status since | 6 May 2026 |
| Application filed | 11 Sept 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Karnataka Power Transmission Corporation Limited |
| Land area | 51 acres (20.6 ha) |
| Forest land | 4.1 acres (1.6 ha) |
| Project cost | ₹9.9 crore |
| Village / locality | Cheelandavadi Forest |
| Taluk / tehsil | Kanakapura |
| District | Ramanagara |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-06923 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 11 Dec 2025 | Decision issued | 51 acres | ₹9.9 crore |
| New project filed 11 Sept 2025 (this page) | Initial checks | 51 acres | ₹9.9 crore |
In context
5 applications in Ramanagara since January 2022 are in the same category (Power): 0 approved, 3 filed or under review, and 2 withdrawn, lapsed or rejected.
18 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Cheelandavadi Forest, Kanakapura, Ramanagara, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.1066 Ha of Wild sanctuary protected land for laying 132/66kV… — decision issued, 0 m away
- Diversion of 0.1066 ha forest land in Sy No. 1 of Cheelandavadi Village,… — lapsed, 0 m away
- Diversion of 0.1066 ha forest land in Sy No. 1 of Cheelandavadi Village,… — more information requested, 0 m away
- Laying of Underground OFC Cable to the Proposed 4G Saturation Site at Hoolya. — under wildlife review, 1.5 km away
- Laying of Underground OFC Cable to the Proposed 4G Saturation Site at Hoolya. — initial checks, 1.5 km away
- Laying of Underground OFC Cable to the Proposed 4G Saturation Site at Hoolya. — initial checks, 1.8 km away
- Laying of Underground OFC Cable to the Proposed 4G Saturation Site at Hoolya. — more information requested, 1.8 km away
- Ofc Route to Usof 4g Bts (Base Transiver Station )hoolya Saturation Project… — more information requested, 1.8 km away
More from Karnataka Power Transmission Corporation Limited in Ramanagara
- Diverted of 1.8 Ha forest land — lapsed
- Diversion of 0.1066 ha forest land in Sy No. 1 of Cheelandavadi Village,… — lapsed
- Diversion of 0.1066 ha forest land in Sy No. 1 of Cheelandavadi Village,… — more information requested
5 Karnataka Power Transmission Corporation projects in Ramanagara
All 32 Karnataka Power Transmission Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.