Stone quarry proposal of Mr. Sanjay Suresh Desai, Gut No-219,220,221 Part Village Antwadi, Ta-Karad, Dist- Satara is an approved mining project in Antvadi, Karad, Satara, Maharashtra. The site covers 2.5 acres.
Who is building it?
The applicant is Sanjay Desai.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Jan 2024), as of 27 Nov 2026.
Where is it?
In Antvadi, Karad, Satara, Maharashtra.
How big is it?
It has a stated cost of ₹65 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 3 Jan 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Jan 2024 |
| Application filed | 3 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Sanjay Desai |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹65 lakh |
| Village / locality | Antvadi |
| Taluk / tehsil | Karad |
| District | Satara |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-00402 |
In context
127 applications in Satara since January 2022 are in the same category (Mining): 100 approved, 9 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 2.5 acres, this one is smaller than 69% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Antvadi, Karad, Satara, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance granted by the name of Mr. Sanjay Suresh… — environmental approval granted, 0 m away
- Environmental Clearance for the Basalt Stone Quarry of Shri. Amit Mansing… — environmental approval granted, 4.1 km away
- Diversion of Forest Land for Laying of Overhead 11 KV Transmission Line From… — under forest review, 4.5 km away
- Environmental Clearance for the stone quarry of Sou. Vanita Shankar Khabale — environmental approval granted, 12.3 km away
- Proposed Manufacturing Unit for the Production of Synthetic Organic Chemicals… — under environmental review, 12.6 km away
- Waste management project by M/s. Karad Hospital Association (CBMWT&DF) — environmental approval granted, 12.7 km away
- Waste management project by M/s. Karad Hospital Association (CBMWT&DF) — environmental approval granted, 12.7 km away
- Diversion of Forest Land for Six Laning of Kagal -Satara Section of NH-48 (Old… — in-principle approval, conditions pending, 12.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.