What is this project?
Environmental Clearance for the Basalt Stone Quarry of Shri. Amit Mansing Pawar located at gut no. 727 part, Village Vadoli Nileshwar, Taluka Karad, District Satara is an approved mining project in Vadoli Nileshwar, Karad, Satara, Maharashtra. The site covers 3 acres.
Who is building it?
The applicant is Pawar Amit Mansing.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 17 Mar 2026), as of 27 Nov 2026.
Where is it?
In Vadoli Nileshwar, Karad, Satara, Maharashtra.
How big is it?
It has a stated cost of ₹64 lakh and a site of 3 acres.
When was it filed?
The application was filed on 4 Feb 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 17 Mar 2026 |
| Application filed | 4 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Pawar Amit Mansing |
| Land area | 3 acres (1.2 ha) |
| Project cost | ₹64 lakh |
| Village / locality | Vadoli Nileshwar |
| Taluk / tehsil | Karad |
| District | Satara |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12739 |
In context
127 applications in Satara since January 2022 are in the same category (Mining): 100 approved, 9 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 3 acres, this one is smaller than 56% of them.
No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.
Where it is
Vadoli Nileshwar, Karad, Satara, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance granted by the name of Mr. Sanjay Suresh… — environmental approval granted, 4.1 km away
- Stone quarry proposal of Mr. Sanjay Suresh Desai, Gut No-219,220,221 Part… — environmental approval granted, 4.1 km away
- Diversion of Forest Land for Laying of Overhead 11 KV Transmission Line From… — under forest review, 5.5 km away
- Environmental Clearance for the stone quarry of Sou. Vanita Shankar Khabale — environmental approval granted, 8.9 km away
- Proposed Manufacturing Unit for the Production of Synthetic Organic Chemicals… — under environmental review, 9 km away
- Waste management project by M/s. Karad Hospital Association (CBMWT&DF) — environmental approval granted, 9.6 km away
- Waste management project by M/s. Karad Hospital Association (CBMWT&DF) — environmental approval granted, 9.6 km away
- Diversion of Forest Land for Six Laning of Kagal -Satara Section of NH-48 (Old… — in-principle approval, conditions pending, 9.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.