Quick answers
What is this project?
1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 4 X 650 TPD is a withdrawn industrial project in Wadla Peth, Aheri, Gadchiroli, Maharashtra. The site covers 342.9 acres.
Who is building it?
The applicant is Surjagad Ispat Private Limited.
Has it been approved?
No. The application was withdrawn on 8 Aug 2024, so it is no longer under consideration.
Where is it?
In Wadla Peth, Aheri, Gadchiroli, Maharashtra.
How big is it?
It has a stated cost of ₹2,752.8 crore and a site of 342.9 acres.
When was it filed?
The application was filed on 8 Aug 2024.
Project details
| Official title | Establishment of 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 4 X 650 TPD along with the installation of Induction Furnace of (0.75 MTPA), Rolling Mill (0.75 MTPA) and Captive Power Plant of capacity 120 MW |
|---|---|
| Status | Withdrawn |
| Status since | 8 Aug 2024 |
| Application filed | 8 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Surjagad Ispat Private Limited |
| Land area | 342.9 acres (138.8 ha) |
| Project cost | ₹2,752.8 crore |
| Village / locality | Wadla Peth |
| Taluk / tehsil | Aheri |
| District | Gadchiroli |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-00979 |
In context
30 applications in Gadchiroli since January 2022 are in the same category (Industry): 15 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 342.9 acres, this one is larger than 50% of them.
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Wadla Peth, Aheri, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sponge Iron Plant of 4 X 650 TPD by M/s. Surjagad Ispat Pvt. Ltd — withdrawn, 0 m away
- 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 8 X… — under environmental review, 400 m away
- 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 8 X… — more information requested, 400 m away
- 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 8 X… — cleared for impact study, 400 m away
- Diversion of 468.000 Ha. Forest Land for Logistic Integrated Facility of… — lapsed, 3.1 km away
- Diversion of 468.000 Ha. Forest Land for Logistic Integrated Facility of… — lapsed, 3.1 km away
- Diversion of Forest Land for Logistic Facility Intigrated and Employment… — lapsed, 3.3 km away
- EC Transfer of Bori Sand Ghat, Area 1.12 ha, Gut. no. 49, 50, 73 Village-… — environmental approval granted, 3.7 km away
More from Surjagad Ispat Private Limited in Gadchiroli
- 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 8 X… — under environmental review
- Diversion of 468.000 Ha. Forest Land for Logistic Integrated Facility of… — lapsed
- Diversion of 468.000 Ha. Forest Land for Logistic Integrated Facility of… — lapsed
- Diversion of Forest Land for Logistic Facility Intigrated and Employment… — lapsed
- Diversion of 9.13 ha forest land for setting up logistic facilities for… — in-principle approval, conditions pending
- 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 8 X… — more information requested
All 9 Surjagad Ispat projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.