WithdrawnIndustry · Gadchiroli, Maharashtra

1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 4 X 650 TPD

1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 4 X 650 TPD is a withdrawn industrial project in Wadla Peth, Aheri, Gadchiroli, Maharashtra. The site covers 342.9 acres. Its stated project cost is ₹2,752.8 crore. As of 27 Nov 2026, its status is “Withdrawn” (since 8 Aug 2024).

See it on the live map All projects in Gadchiroli

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 4 X 650 TPD is a withdrawn industrial project in Wadla Peth, Aheri, Gadchiroli, Maharashtra. The site covers 342.9 acres.

Who is building it?

The applicant is Surjagad Ispat Private Limited.

Has it been approved?

No. The application was withdrawn on 8 Aug 2024, so it is no longer under consideration.

Where is it?

In Wadla Peth, Aheri, Gadchiroli, Maharashtra.

How big is it?

It has a stated cost of ₹2,752.8 crore and a site of 342.9 acres.

When was it filed?

The application was filed on 8 Aug 2024.

Project details

Official titleEstablishment of 1.6 MTPA Beneficiation plant, 1.2 MTPA Pellet plant & Sponge Iron Plant of 4 X 650 TPD along with the installation of Induction Furnace of (0.75 MTPA), Rolling Mill (0.75 MTPA) and Captive Power Plant of capacity 120 MW
StatusWithdrawn
Status since8 Aug 2024
Application filed8 Aug 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantSurjagad Ispat Private Limited
Land area342.9 acres (138.8 ha)
Project cost₹2,752.8 crore
Village / localityWadla Peth
Taluk / tehsilAheri
DistrictGadchiroli
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-00979

In context

30 applications in Gadchiroli since January 2022 are in the same category (Industry): 15 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 342.9 acres, this one is larger than 50% of them.

12 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Wadla Peth, Aheri, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Surjagad Ispat Private Limited in Gadchiroli

All 9 Surjagad Ispat projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.