One of 2 filings for this project. The project's main page, with every filing and where each stands: "Three Leaves" Residential and Commercial Project by M/s. Deepak Infra and Homes Pvt. Ltd.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 10 May 2023 |
| Application filed | 10 May 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Deepak Infra and Homes Private Limited |
| Land area | 5.7 acres (2.3 ha) |
| Project cost | ₹350.7 crore |
| Village / locality | Nasik |
| Taluk / tehsil | Nashik |
| District | Nashik |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-02448 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 12 Jun 2023 | Environmental approval granted | 5.7 acres | ₹350.7 crore |
| Early planning filed 10 May 2023 (this page) | Cleared for impact study | 5.7 acres | ₹350.7 crore |
What the filings say
What is planned
The applicant, M/s. Deepak Infra and Homes Pvt. Ltd., proposes a new greenfield residential and commercial development named "Three Leaves" in Nashik. The project is planned on a plot of 2.3 hectares (5.68 acres) and involves the construction of five buildings in total.
The project components include:
- Commercial Building A: Basement + Ground + 7 floors (29.40 metres high), containing 40 shops and 158 offices.
- Residential Buildings A, B, and C: Each consisting of a Basement + Ground + 3 Podiums + 32 floors (129.60 metres high), with 128 tenements per building (384 total).
- MHADA Building: Ground + 9 floors (28.50 metres high), containing 68 tenements.
The total planned population for the project is 3,975 persons, comprising 2,595 regular residents, 282 MHADA residents, and 1,098 commercial occupants. The total construction built-up area is 1,67,007.87 square metres.
Layout and design
The project report states the site is sloping from West to East, with the highest contour point at 103.62 metres and the lowest at 99.90 metres. The ground coverage area is 13,301.88 square metres, while 2,202.87 square metres is designated as open space.
Internal movement is designed with a 6.00-metre wide fire tender driveway. The project includes a total of 452 residential tenements and 198 commercial units (shops and offices). Parking is planned across basement and podium levels.
| Item | Detail |
|---|---|
| Total Plot Area | 23,074.02 sq.m. |
| Net Plot Area | 22,016.27 sq.m. |
| Ground Coverage | 13,301.88 sq.m. |
| Total Built-up Area (FSI + Non-FSI) | 1,67,007.87 sq.m. |
| Total Residential Units | 452 |
| Total Commercial Units | 198 |
| Tallest Building Height | 129.60 m |
Land and surroundings
The project is located at Survey No. 789/3 in Nashik, Maharashtra. The site is situated in a residential zone as per the Development Plan. It is bounded by Shanti Garden Park to the North, Chaitnya Apartment B to the East, Shri Niketan Apartment to the South, and a 30.0-metre wide Old Canal Link Road to the West.
The nearest highway is the Mumbai-Nashik Highway (NH 3), located 0.56 km to 1.0 km away. Nashik Railway Station is approximately 10.0 km from the site, and Nashik Airport is about 24.0 km away. The Nasardi River flows approximately 0.35 km to the North.
Water, power and access
Water: During the operation phase, the total water requirement is estimated at 431.0 Kilo Litres per Day (KLD). The Nashik Municipal Corporation (NMC) will supply 271.0 KLD of fresh water for domestic use. The remaining 160 KLD (144 KLD for flushing and 16 KLD for gardening) will be met using treated wastewater from on-site Sewage Treatment Plants (STPs). Two STPs are proposed with capacities of 380 KLD and 40 KLD. Excess treated wastewater (177 KLD in dry weather) will be discharged into the municipal sewer.
Power: The maximum power demand is 4,177.0 kW, to be sourced from the Maharashtra State Electricity Distribution Company Limited (MSEDCL). For backup, four Diesel Generator (DG) sets are planned (two of 450 kVA and two of 631 kVA). Energy-saving measures include LED lighting, V3F drives for lifts, and a 165 kW Solar Photo-Voltaic (PV) system. Solar water heating is planned for 14,250 litres per day.
Environmental safeguards
Waste Management: The project is expected to generate 1,610 kg/day of solid waste during operation. This includes 926 kg/day of biodegradable waste, which will be treated in an on-site Organic Waste Converter (OWC), and 684 kg/day of non-biodegradable waste to be handed over to authorized recyclers or the municipal corporation. During construction, 56,250 cubic metres of soil will be excavated; 3,250 cubic metres will be reused on-site, and the remainder will be transported to a designated site in Chandsi, Nashik.
Air and Noise: Dust suppression during construction will involve tin sheet barricading, safety nets, and covering transport trucks. High-noise activities are restricted to daytime, and workers will be provided with ear muffs.
Green Belt: The applicant proposes to plant trees as part of the landscape plan, utilizing 3,465 cubic metres of topsoil preserved from excavation. Rainwater harvesting is planned through pits to recharge groundwater.
Deepak Infra and Homes "Three Leaves" Residential and Commercial site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
93 applications in Nashik since January 2022 are in the same category (Buildings & townships): 59 approved, 12 filed or under review, and 22 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 5.7 acres, this one is larger than 56% of them.
53 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nasik, Nashik, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Three Leaves" Residential and Commercial Project by M/s. Deepak Infra and… — environmental approval granted, 0 m away
- "Three Leaves" -Residential and Commercial Development- by M/s. Deepak Infra… — cleared for impact study, 0 m away
- "Quillion Park" - EXPANSION OF RESIDENTIAL AND COMMERCIAL DEVELOPMENT by M/s.… — environmental approval granted, 450 m away
- "Quillion Park" - EXPANSION OF RESIDENTIAL AND COMMERCIAL DEVELOPMENT by M/s.… — environmental approval granted, 450 m away
- "Quillion Park" - EXPANSION OF RESIDENTIAL AND COMMERCIAL DEVELOPMENT by M/s.… — cleared for impact study, 450 m away
- "Quillion Park" - EXPANSION OF RESIDENTIAL AND COMMERCIAL DEVELOPMENT by M/s.… — cleared for impact study, 450 m away
- Amendment & Expansion in Environmental Clearance of Proposed Residential cum… — lapsed, 500 m away
- Amendment & Expansion in Environmental Clearance of Proposed Residential cum… — withdrawn, 500 m away
More from Deepak Infra and Homes Private Limited in Nashik
- Amendment & Expansion in Environmental Clearance of Proposed Residential cum… — lapsed
- Amendment & Expansion in Environmental Clearance of Proposed Residential cum… — withdrawn
- Proposed Commercial complex at P. No. 1+2+3+4, S.No. 7/1 to 7/5 + 8 / 1 to… — lapsed
- Residential cum Commercial Project (Amendment) "Star Apex" on Plot Bearing S.… — environmental approval granted
- Residential cum Commercial Project (Amendment) "Star Apex" on Plot Bearing S.… — withdrawn
- "Three Leaves" -Residential and Commercial Development- by M/s. Deepak Infra… — cleared for impact study
All 8 Deepak Infra and Homes projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.