Quick answers
What is this project?
Coal to Chemicals including Coal-To-Syngas, Hydrogen, Methanol/DME and Urea is a proposed industrial project in Gourala, Bhadravati, Chandrapur, Maharashtra. The site covers 1,575.2 acres.
Who is building it?
The applicant is New Era Cleantech Solution Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 27 Jul 2023), as of 27 Nov 2026.
Where is it?
In Gourala, Bhadravati, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹20,000 crore and a site of 1,575.2 acres.
When was it filed?
The application was filed on 27 Jul 2023.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 27 Jul 2023 |
| Application filed | 27 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | New Era Cleantech Solution Private Limited |
| Land area | 1,575.2 acres (637.5 ha) |
| Project cost | ₹20,000 crore |
| Village / locality | Gourala |
| Taluk / tehsil | Bhadravati |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-02858 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 9 Dec 2025 | Initial checks | 1,575.2 acres | ₹20,000 crore |
| Early planning filed 27 Jul 2023 (this page) | Cleared for impact study | 1,575.2 acres | ₹20,000 crore |
In context
55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1,575.2 acres, this one is larger than 96% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gourala, Bhadravati, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Coal to Chemicals including Coal-To-Syngas, Hydrogen, Methanol/DME and Urea — initial checks, 0 m away
- Coal to Chemicals including Coal-To-Syngas, Hydrogen, Methanol/DME and Urea — environmental approval granted, 800 m away
- Environmental Clearance for Proposed Expansion of Steel Plant Comprising of… — under environmental review, 3.4 km away
- The Proposed Bhandak West Coal Mine, Villa ge Kesurli, Kuroda & Vijasan Tehsil… — cleared for impact study, 3.6 km away
- The Proposed Bhandak West Coal Mine, Villa ge Kesurli, Kuroda & Vijasan Tehsil… — forest land use approved, 3.6 km away
- Revalidation of prior EC of Pipri de Sand Ghat, Area 4.50 ha, Gut. no. 45 to… — environmental approval granted, 6 km away
- EC Transfer of Pipri de Sand Ghat, Area 4.50 ha, Gut. no. 45 to 50, 52 to 57,… — environmental approval granted, 6 km away
- Pipri de Sand Ghat, Area 4.50 ha, Gut. no. 45 to 50, 52 to 57, Village Pipri… — environmental approval granted, 6 km away
More from New Era Cleantech Solution Private Limited in Chandrapur
- The Proposed Bhandak West Coal Mine, Villa ge Kesurli, Kuroda & Vijasan Tehsil… — cleared for impact study
- The Proposed Bhandak West Coal Mine, Villa ge Kesurli, Kuroda & Vijasan Tehsil… — forest land use approved
- Coal to Chemicals including Coal-To-Syngas, Hydrogen, Methanol/DME and Urea — environmental approval granted
All 5 New Era Cleantech Solution projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.