Proposed Green Field Project for Manufacturing of 9,00,000 TPA of Sponge Iron (4 X 650 TPD DRI kiln), 8,00,000 TPA of Billets by 8 X 30 T Induction Furnace, 8,80,000 TPA of Rolled Products, TMT etc by Rolling Mill (7,80,000 TPA Direct Hot Charging and 1,00,000 TPA RHF Route), Captive Power generation of 75 MW through WHRB and 25 MW through AFBC and Slag Crusher (For Sand Making) (1,00,000 TPA) by M/s. Icon Steels India Private Limited is a proposed industrial project in Khapari, Warora, Chandrapur, Maharashtra. The site covers 305.1 acres.
Who is building it?
The applicant is Icon Steel India Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 6 Nov 2024), as of 27 Nov 2026.
Where is it?
In Khapari, Warora, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹1,800 crore and a site of 305.1 acres.
When was it filed?
The application was filed on 11 Sept 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 6 Nov 2024 |
| Application filed | 11 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Icon Steel India Private Limited |
| Land area | 305.1 acres (123.5 ha) |
| Project cost | ₹1,800 crore |
| Village / locality | Khapari |
| Taluk / tehsil | Warora |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-06104 |
In context
55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 305.1 acres, this one is larger than 76% of them.
Where it is
Khapari, Warora, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 2 x150 DRI Kilns for 99000 TPA of Sponge Iron Production and 11 MW Power Plant… — cleared for impact study, 7.6 km away
- Praposal for Critical Wildlife Habitat Declaring in Tadoba National Park — under wildlife review, 10.2 km away
- Revalidation of prior EC of Parodhi-1Sand Ghat, Area 1.05 ha, Gut. no. 128 to… — environmental approval granted, 12.3 km away
- EC Transfer of Parodhi-1 Sand Ghat, Area 1.05 ha, Gut. no. 128 to 131, 154,… — environmental approval granted, 12.3 km away
- Parodhi-1Sand Ghat, Area 1.05 ha, Gut. no. 128 to 131, 154, 156, Village… — environmental approval granted, 12.3 km away
- Wildlife Clearance Proposal and Its Approval From Nbwl, Gov of India for… — more information requested, 14.9 km away
- Wildlife Clearance Proposal and Its Necessary Approval From Nbwl, Govt. of… — more information requested, 18.2 km away
- Revalidation of prior EC of Usegaon Sand Ghat, Area 2.75 ha, Gut. no. 310,… — environmental approval granted, 21.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.