Project details
| Official title | "Proposed Infra Development in Wadachiwadi Town Planning Scheme no. 2" at Village- Wadachiwadi, Tal- Haveli, Dist. - Pune, Maharashtra- 411060 And "Proposed Infra Development in Aautade Handewadi Town Planning Scheme no. 3" at Village-Aautade Handewadi, Tal- Haveli, Dist. - Pune, Maharashtra- 411028 |
|---|---|
| Status | Cleared for impact study |
| Status since | 20 Jul 2024 |
| Application filed | 9 Jul 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Pune Metropolitan Region Development Authority |
| Use | Township |
| Land area | 566.3 acres (229.2 ha) |
| Built-up area | 4,11,060 m² (44,24,609 sq ft) |
| Plot area | 22,91,900 m² (2,46,69,782 sq ft) |
| Project cost | ₹750 crore |
| Village / locality | Autadwadi Handewadi |
| Taluk / tehsil | Haveli |
| District | Pune |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-06298 |
What the filings say
What is planned
The Pune Metropolitan Region Development Authority (PMRDA) is proposing a large-scale infrastructure development across two adjacent town planning schemes: Wadachiwadi Town Planning Scheme (TPS) No. 2 and Aautade-Handewadi TPS No. 3. The combined project area covers 229.19 hectares (566.34 acres) in the Haveli taluk of Pune.
The project is an area development scheme where PMRDA acts as the special planning authority. It involves pooling land from various owners, reconstituting it into planned plots, and providing comprehensive common infrastructure. The applicant's project report states that the primary goal is to facilitate planned urban growth and implement a 65-metre wide Ring Road sanctioned in the Regional Plan.
Components and Land Use
The total area is divided between the two schemes as follows:
- Wadachiwadi TPS 2: 134.79 hectares
- Aautade-Handewadi TPS 3: 94.40 hectares
Under the proposed layout, approximately 47.93% of the total land (109.84 hectares) will be returned to private landowners as final plots. The remaining area is reserved for public purposes, including:
- Roads: 39.39 hectares (17.19% of total area), including the 65m Ring Road.
- Economically Weaker Section (EWS) Housing: 20.18 hectares (8.80%).
- Gardens and Open Spaces: 18.48 hectares (8.06%).
- Authority Plots for Sale: 16.18 hectares (7.06%).
- Public Amenities and Utilities: 12.39 hectares (5.41%).
Layout and design
The road network is designed with a hierarchy of arterial, feeder, and neighbourhood streets. The 65m Ring Road passes through both schemes, dividing the area into two parts. Other proposed roads range in width from 9m to 24m. The layout includes 204 original plots which will be reconstituted into 342 final plots.
Specific reservations include plots for a fire station, water treatment plant, elevated service reservoirs, solid waste conveyance, a sewage treatment plant, cremation grounds, electric substations, and markets. Educational and health facilities, including primary schools and a maternity home, are also integrated into the plan.
Land and surroundings
The project site is located south-southeast of Pune city, adjacent to the Pune Municipal Corporation boundary. The topography of TPS 2 is gentle with a hill towards the south, while TPS 3 is largely plain with a gentle northward slope. Currently, the land is primarily in an agricultural zone, though much of it is not actively farmed.
Environmental sensitivities within a 10km radius include the Rajiv Gandhi Zoological Park (6.30 km), Empress Botanical Garden (8.80 km), and several lakes such as Mastani Lake and Katraj Lake. Approximately 50% of the Wadachiwadi Lake (also known as Pisoli Hill Lake) is located within the southern portion of the TPS 2 project site.
Water, power and access
Water Supply
The total water requirement for the operational phase is estimated at 58.72 million litres per day (MLD). This includes 35.42 MLD for domestic use and 18.82 MLD for flushing. PMRDA proposes a 32 MLD Water Treatment Plant (WTP) and four Elevated Service Reservoirs (ESR) with a combined capacity of approximately 6.07 MLD. During construction, water will be sourced from tankers or existing borewells.
Sewerage and Drainage
A common Sewage Treatment Plant (STP) with a capacity of 21.0 MLD is planned for plots that do not require individual environmental clearance. Larger plots (EC plots) are expected to provide their own STPs. The storm water network will include 36.39 km of drains and several box culverts to manage runoff, particularly around the existing nallas.
Power and Access
Power will be sourced from a transmission line approximately 28 km away at Lonikand (Wagholi). The internal distribution network will cover 18.2 km, supported by a new substation. Street lighting will be provided, with a preference for solar-powered units. The site is accessible via State Highway 116 (Katraj to Fursungi) and is approximately 16.4 km from Pune International Airport.
Environmental safeguards
The applicant plans to plant approximately 12,753 trees across roads, open spaces, and gardens. This includes compensatory planting at a 1:5 ratio for the 297 trees proposed to be cut during development. Native species will be prioritized.
For solid waste, a four-zone collection system is proposed. Wet waste from non-EC plots will be treated at the Pune Municipal Corporation's Moshi facility, while EC plots must provide their own Organic Waste Converters (OWC). Construction waste, including an estimated 17.18 lakh cubic metres of excavated material, will be reused for road gardening and plinth filling where possible.
Timeline
The infrastructure development is planned in four phases. PMRDA intends to self-fund the first two phases, with subsequent phases funded through the sale of authority plots. The estimated total cost for infrastructure is ₹750 crore (₹400 crore for TPS 2 and ₹350 crore for TPS 3).
Proposed Infra Development in Wadachiwadi Town Planning Scheme No. 2 site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
3,029 applications in Pune since January 2022 are in the same category (Buildings & townships): 2,001 approved, 415 filed or under review, and 613 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 566.3 acres, this one is larger than 99% of them.
188 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Autadwadi Handewadi, Haveli, Pune, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Pune Ring Road Eastern Alignment (Part 2): 68.8 km Expressway Expansion in Pune, Maharashtra (8.8 km away).
Other projects nearby
- Proposed Expansion for Residential Project "Mayuri Adinath" located at Survey… — environmental approval granted, 1.3 km away
- Proposed Expansion for Residential Project "Mayuri Adinath" located at Survey… — returned to applicant, 1.3 km away
- Mr. Rohidas Raghunath Ghule — not approved, 1.4 km away
- Proposed Residential & Commercial Project at S. no. 52, H. No. 7K/1, 7K/2,… — environmental approval granted, 1.5 km away
- Expansion of Residential Project "38 PARK" at S. No. 38-2+3, Village: Undri,… — environmental approval granted, 1.6 km away
- Proposed Residential & commercial project at S.No. 55, H.No. 3B/1, Plot A,… — environmental approval granted, 1.6 km away
- Proposed Residential & commercial project at S. No. 55, H. No. 3B/1, Plot A,… — lapsed, 1.6 km away
- Proposed Residential & commercial project at S.No. 55, H.No. 3B/1, Plot A,… — lapsed, 1.6 km away
More from Pune Metropolitan Region Development Authority in Pune
- Diversion of Reserved Forest area for Construction of Major Bridge on Theur… — under forest review
- Diversion of Forest Area for Laying of Underground Water Supply Pipeline From… — lapsed
- Diversion of Forest area for construction of Pune Inner Ring Road Project from… — lapsed
- "Proposed Infra Development in Holkarwadi Town Planning Scheme No. 4 and in… — cleared for impact study
- Diversion of 20.9 Ha. Forest Area for Construction and Widening of Existing… — more information requested
- Diversion of 23.5 Ha. Forest Area for Construction and Widening of Existing… — lapsed
All 12 Pune Metropolitan Region Development Authority projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.